1442-1444 E 20TH ST 90011

Certificate Information: 1442-1444 E 20TH ST 90011

Application / Permit
24010-20000-02922
Plan Check / Job No.
B24VN09940
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN: NEW IRREGULAR SHAPED 107'-4" x 21'-6" 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 1/7/2025
Issuing Office
Current Status
CofO Issued on 6/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 ALFRED RAMIREZ
Corrections Issued 7/22/2024 ALFRED RAMIREZ
Quality Review Completed 7/25/2024 STEVEN KIM
Applicant returned to address corrections 12/17/2024 ALFRED RAMIREZ
Plan Check Approved 12/19/2024 ALFRED RAMIREZ
Issued 1/7/2025 APPLICANT
CofO in Progress 6/28/2025 ALEJANDRO DE ARTOLA
Permit Finaled 6/29/2025 DEROLD HAUFF
Permit Finaled 6/29/2025 DEROLD HAUFF
CofO Issued 6/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2024 CELINA MORENO
Permit Cleared 8/22/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/3/2024 CELINA MORENO
Sewer availability Cleared 9/3/2024 CELINA MORENO
Low Impact Development (LID) Cleared 9/12/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 10/10/2024 CELINA MORENO
Hydrant and Access approval Cleared 11/1/2024 JERRY KAO
Trees in Parkway Cleared 11/25/2024 MIGUEL ORNELAS

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/27/2025 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 2/27/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval MICHAEL LEWIS
Insulation 2/28/2025 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/21/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/22/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 4/22/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/22/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/22/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/23/2025 Approved ALEJANDRO DE ARTOLA
Insulation 4/23/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/1/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 5/1/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 6/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 6/26/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/27/2025 Approved ALEJANDRO DE ARTOLA
Final 6/27/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 6/27/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/27/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/27/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 6/27/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 6/27/2025 Approved ALEJANDRO DE ARTOLA