5952-5952 1/2 N BALCOM AVE 91316

Certificate Information: 5952-5952 1/2 N BALCOM AVE 91316

Application / Permit
24010-20000-02917
Plan Check / Job No.
B24VN09927
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY 588 SQFT SINGLE FAMILY DWELLING PER SB9 W/ATTACHED ADU (588 SQFT) PER LAMC 12.22 A.33(c)(e) W/NFPA 13D SPRINKLERS REQUIRED THROUGHOUT. ALL ELECTRIC BUILDING. WORK DONE USING WFPP
Permit Issued
Issued on 11/26/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 PETER MOSESIAN
Corrections Issued 7/25/2024 PETER MOSESIAN
Quality Review Completed 7/29/2024 OMID HEDAYAT
Building Plans Picked Up 7/31/2024 APPLICANT
Plan Check Approved 11/26/2024 PETER MOSESIAN
Issued 11/26/2024 APPLICANT
CofO in Progress 10/6/2025 MORRIS JACKSON
Permit Finaled 10/7/2025 JOHN JANSON
CofO Issued 10/7/2025 JOHN JANSON
Permit Finaled 10/7/2025 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 8/1/2024 WALTER RAMIREZ
Address approval Cleared 8/2/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 8/2/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 8/2/2024 EDGAR ALCARAZ
Sewer availability Cleared 8/2/2024 EDGAR ALCARAZ
Senate Bill 9 Cleared 8/27/2024 DORIAN AGUILAR
ZI Cleared 10/7/2024 DORIAN AGUILAR
Hydrant and Access approval Cleared 11/21/2024 JERRY KAO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/13/2024 Corrections Issued MORRIS JACKSON
Sewer 12/13/2024 Approved MORRIS JACKSON
Underground Mechanical 12/13/2024 Partial Approval MORRIS JACKSON
Footing/Foundation/Slab 12/23/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 1/29/2025 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 1/29/2025 Approved MORRIS JACKSON
Green Building Rough 1/29/2025 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 1/29/2025 Corrections Issued MORRIS JACKSON
Verify Sprinkler Sign Off 1/29/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 3/5/2025 Corrections Issued MORRIS JACKSON
Green Building Rough 3/5/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 3/5/2025 Approved MORRIS JACKSON
PLUMBING-Rough 3/5/2025 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 3/5/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 4/4/2025 Not Ready for Inspection MORRIS JACKSON
Green Building Rough 4/4/2025 Not Ready for Inspection MORRIS JACKSON
Insulation 4/4/2025 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 4/4/2025 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 4/10/2025 Approved JON MCHUGH
Green Building Rough 4/10/2025 Approved JON MCHUGH
Insulation 4/10/2025 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 4/10/2025 Partial Approval JON MCHUGH
Insulation 4/17/2025 Approved MORRIS JACKSON
Drywall Nailing 4/23/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 4/23/2025 Approved MORRIS JACKSON
Final 9/8/2025 Corrections Issued MORRIS JACKSON
Green Building Final 9/8/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Not Required MORRIS JACKSON
Service/Power Release 9/8/2025 Approved MORRIS JACKSON
Smoke Detectors 9/8/2025 Approved MORRIS JACKSON
Final 9/16/2025 OK to Issue CofO MORRIS JACKSON