8980 W OSWEGO ST 91040
Certificate Information: 8980 W OSWEGO ST 91040
- Application / Permit
- 24010-20000-02900
- Plan Check / Job No.
- B24VN09884
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 1-story Accessory Dwelling Unit (33'-11" x 22'-6" Irregular Shape) per LAMC 12.22 A.33 (c) - (d)
- Permit Issued
- Issued on 11/3/2024
- Issuing Office
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 8/7/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 8/12/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/29/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 11/1/2024 | VAHAN JIVALAGIAN |
| Issued | 11/3/2024 | APPLICANT |
| CofO in Progress | 1/29/2026 | KEVIN BERBERYAN |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
| CofO Issued | 1/30/2026 | RUBEN SALAS |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/18/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/18/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 9/20/2024 | LAVEON RIDER |
| GPI Written Notices | Cleared | 10/29/2024 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 10/29/2024 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2025 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 5/20/2025 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 5/29/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/17/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 6/30/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 6/30/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 6/30/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 8/1/2025 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 8/1/2025 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 8/19/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/19/2025 | Approved | WILLIAM WREN |
| Deputy Wood Construction | 8/20/2025 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 8/29/2025 | Approved | WILLIAM WREN |
| HVAC-Final | 8/29/2025 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 8/29/2025 | Approved | WILLIAM WREN |
| Insulation | 9/5/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/5/2025 | Partial Approval | WILLIAM WREN |
| Drywall Nailing | 9/12/2025 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 9/17/2025 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 9/17/2025 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 10/29/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Service/Power Release | 11/3/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 11/13/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 11/13/2025 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/13/2025 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 11/13/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 11/13/2025 | Approved | DAVID ANDERSON |
| Final | 11/18/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 11/18/2025 | Corrections Issued | WILLIAM WREN |
| Service/Power Release | 11/18/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 11/19/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Final | 11/19/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 11/19/2025 | Approved | KEVIN BERBERYAN |
| Final | 1/29/2026 | OK to Issue CofO | KEVIN BERBERYAN |