8980 W OSWEGO ST 91040

Certificate Information: 8980 W OSWEGO ST 91040

Application / Permit
24010-20000-02900
Plan Check / Job No.
B24VN09884
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 1-story Accessory Dwelling Unit (33'-11" x 22'-6" Irregular Shape) per LAMC 12.22 A.33 (c) - (d)
Permit Issued
Issued on 11/3/2024
Issuing Office
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 VAHAN JIVALAGIAN
Corrections Issued 8/7/2024 VAHAN JIVALAGIAN
Quality Review Completed 8/12/2024 OMID HEDAYAT
Applicant returned to address corrections 10/29/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/1/2024 VAHAN JIVALAGIAN
Issued 11/3/2024 APPLICANT
CofO in Progress 1/29/2026 KEVIN BERBERYAN
Permit Finaled 1/30/2026 RUBEN SALAS
CofO Issued 1/30/2026 RUBEN SALAS
Permit Finaled 1/30/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/18/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/18/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/18/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/18/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 9/20/2024 LAVEON RIDER
GPI Written Notices Cleared 10/29/2024 VAHAN JIVALAGIAN
Grading Pre-Inspection Cleared 10/29/2024 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2025 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 5/20/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 5/29/2025 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/17/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/30/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 6/30/2025 Approved WILLIAM WREN
PLUMBING-Rough 6/30/2025 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Corrections Issued WILLIAM WREN
Green Building Rough 8/1/2025 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 8/1/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 8/19/2025 Approved WILLIAM WREN
PLUMBING-Rough 8/19/2025 Approved WILLIAM WREN
Deputy Wood Construction 8/20/2025 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 8/29/2025 Approved WILLIAM WREN
Green Building Rough 8/29/2025 Approved WILLIAM WREN
HVAC-Final 8/29/2025 Approved WILLIAM WREN
Verify Sprinkler Sign Off 8/29/2025 Approved WILLIAM WREN
Insulation 9/5/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 9/5/2025 Partial Approval WILLIAM WREN
Drywall Nailing 9/12/2025 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/17/2025 Approved JOAQUIN GREENOUGH
Shower Pan 9/17/2025 Approved JOAQUIN GREENOUGH
Service/Power Release 10/29/2025 Corrections Issued JOAQUIN GREENOUGH
Service/Power Release 11/3/2025 Not Ready for Inspection WILLIAM WREN
Final 11/13/2025 Corrections Issued DAVID ANDERSON
Green Building Final 11/13/2025 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Not Required DAVID ANDERSON
Service/Power Release 11/13/2025 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 11/13/2025 Approved DAVID ANDERSON
Final 11/18/2025 Corrections Issued WILLIAM WREN
Green Building Final 11/18/2025 Corrections Issued WILLIAM WREN
Service/Power Release 11/18/2025 Not Ready for Inspection WILLIAM WREN
Final 11/19/2025 Partial Approval KEVIN BERBERYAN
Green Building Final 11/19/2025 Approved KEVIN BERBERYAN
Service/Power Release 11/19/2025 Approved KEVIN BERBERYAN
Final 1/29/2026 OK to Issue CofO KEVIN BERBERYAN