10280-10282 N HADDON AVE 91331
Certificate Information: 10280-10282 N HADDON AVE 91331
- Application / Permit
- 24010-20000-02889
- Plan Check / Job No.
- B24VN09485
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW TWO STORY TWO UNIT ADU PER STATE LAW FOR MULTI FAMILY CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) NFPA 13D SPRINKLERED THOUGH OUT
- Permit Issued
- Issued on 2/11/2025
- Issuing Office
- Current Status
- Issued on 2/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | JAD BASMA |
| Corrections Issued | 7/14/2024 | JAD BASMA |
| Quality Review Completed | 7/30/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 10/23/2024 | JAD BASMA |
| Applicant returned to address corrections | 11/5/2024 | JAD BASMA |
| Plan Check Approved | 2/10/2025 | JAD BASMA |
| Issued | 2/11/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2024 | LEE GUILBEAUX |
| Permit | Cleared | 7/18/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/18/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/2/2024 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 9/30/2024 | ADALBERTO VERA |
| Construction near power lines | Cleared | 10/3/2024 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 10/3/2024 | SARAH YOUSSEF |
| Clean Up Green Up | Cleared | 10/15/2024 | ASHLEY RODARTE |
| Roof/Waste drainage to street | Cleared | 10/17/2024 | LEE GUILBEAUX |
| SB8 RUD | Cleared | 2/7/2025 | JULIE LIEU |
Contact Information
| Contractor | Ikon Development Corp; Lic. No.: 1033081-B | , |
| Contractor | Ikon; Lic. No.: 1033081-B | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 8/19/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 8/19/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/23/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 8/26/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/26/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 8/26/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/11/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/11/2025 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 12/11/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 12/11/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 12/11/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/11/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/11/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/22/2025 | Approved | MICHEL ABAJAN |
| Insulation | 12/22/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/5/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/2/2026 | Approved | MICHEL ABAJAN |
| Gas Test | 3/9/2026 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Not Ready | MICHEL ABAJAN |
| Sewer | 3/9/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/9/2026 | Approved | MICHEL ABAJAN |