7823 N FERNCOLA AVE 91352

Certificate Information: 7823 N FERNCOLA AVE 91352

Application / Permit
24010-20000-02865
Plan Check / Job No.
B24VN09709
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY (30'-5"x22'-0"), 1199 SQFT ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)(d). ALL ELECTRIC BUILDING
Permit Issued
Issued on 8/26/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 PETER MOSESIAN
Corrections Issued 7/21/2024 PETER MOSESIAN
Quality Review Completed 7/23/2024 OMID HEDAYAT
Building Plans Picked Up 7/29/2024 APPLICANT
Plan Check Approved 8/15/2024 PETER MOSESIAN
Issued 8/26/2024 APPLICANT
CofO in Progress 6/13/2025 DAVID ANDERSON
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/3/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/3/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/5/2024 CARLOS AGUILERA
Sewer availability Cleared 8/5/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/17/2024 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 9/17/2024 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 10/7/2024 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 10/9/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 2/3/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Corrections Issued DAVID ANDERSON
HVAC-Rough 2/3/2025 Approved DAVID ANDERSON
PLUMBING-Rough 2/3/2025 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 2/4/2025 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 2/7/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Approved DAVID ANDERSON
PLUMBING-Rough 2/7/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/5/2025 Approved DAVID ANDERSON
Green Building Rough 3/5/2025 Approved DAVID ANDERSON
Insulation 3/5/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 3/5/2025 Partial Approval DAVID ANDERSON
Verify Sprinkler Sign Off 3/5/2025 Approved DAVID ANDERSON
Drywall Nailing 3/14/2025 Approved DAVID ANDERSON
Shower Pan 3/14/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 3/24/2025 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 4/2/2025 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 4/7/2025 Approved MICHAEL CORTEZ
Sewer 4/7/2025 Not Ready for Inspection MICHAEL CORTEZ
Sewer 4/16/2025 Corrections Issued DAVID ANDERSON
Sewer 4/22/2025 Approved KEVIN BERBERYAN
Underground Mechanical 5/22/2025 Approved DAVID ANDERSON
Final 6/9/2025 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 6/9/2025 Approved DAVID MATSON
Green Building Final 6/9/2025 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Not Required DAVID MATSON
Service/Power Release 6/9/2025 Not Ready for Inspection DAVID MATSON
Smoke Detectors 6/9/2025 Corrections Issued DAVID MATSON
ELECTRICAL-Final 6/12/2025 Approved DAVID ANDERSON
Final 6/12/2025 OK to Issue CofO DAVID ANDERSON
Service/Power Release 6/12/2025 Approved DAVID ANDERSON
Smoke Detectors 6/12/2025 Approved DAVID ANDERSON