12428 W WOODGREEN ST 90066

Certificate Information: 12428 W WOODGREEN ST 90066

Application / Permit
24010-20000-02862
Plan Check / Job No.
B24VN09690
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'-0" X 19'-11" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 1/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 ARTIN ZARUKIAN
Corrections Issued 7/13/2024 ARTIN ZARUKIAN
Building Plans Picked Up 7/16/2024 APPLICANT
Plan Check Approved 11/19/2024 ALEC MOUSAKHANIAN
Issued 1/7/2025 APPLICANT
Permit Finaled 2/24/2026 RICHARD STEINBACH
CofO Issued 2/24/2026 RICHARD STEINBACH
Permit Finaled 2/24/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/22/2024 DINAH GARIN
Grading Pre-Inspection Cleared 7/22/2024 VASIL MIHALEV
Roof/Waste drainage to street Cleared 7/29/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/2/2024 ANDREA SAINT-ANTONIN
Sewer availability Cleared 8/2/2024 ANDREA SAINT-ANTONIN
Specific Plan Cleared 10/2/2024 JOSHUA JONES
Construction near power lines Cleared 11/7/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Partial Approval MICHAEL ALLEN
Green Building Rough 5/19/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 5/19/2025 Partial Approval MICHAEL ALLEN
Verify Sprinkler Sign Off 5/19/2025 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 7/24/2025 Not Ready for Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/24/2025 Approved WILBER ROSALES
Green Building Rough 7/24/2025 Not Ready for Inspection WILBER ROSALES
Verify Sprinkler Sign Off 7/24/2025 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Rough 8/26/2025 Approved WILBER ROSALES
HVAC-Rough 8/26/2025 Approved WILBER ROSALES
PLUMBING-Rough 8/26/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 9/8/2025 Approved WILBER ROSALES
Green Building Rough 9/8/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/8/2025 Approved WILBER ROSALES
Verify Sprinkler Sign Off 9/8/2025 Approved WILBER ROSALES
Insulation 9/12/2025 Not Ready for Inspection WILBER ROSALES
Insulation 9/15/2025 Approved WILBER ROSALES
Shower Pan 9/15/2025 Approved WILBER ROSALES
Drywall Nailing 9/22/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/22/2025 Approved WILBER ROSALES
Gas Test 12/9/2025 Approved WILBER ROSALES
Sewer 12/9/2025 Approved WILBER ROSALES
Underground Mechanical 12/9/2025 Approved WILBER ROSALES
ELECTRICAL-Final 2/4/2026 Approved HERBERT GIRON
HVAC-Final 2/4/2026 Approved HERBERT GIRON
PLUMBING-Final 2/4/2026 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/9/2026 Approved ANTHONY EGSON
Final 2/11/2026 Conditional Approval MICHAEL ALLEN
Footing/Foundation/Slab 2/11/2026 Approved MICHAEL ALLEN
Green Building Final 2/11/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Approved MICHAEL ALLEN
Service/Power Release 2/11/2026 Approved MICHAEL ALLEN
Smoke Detectors 2/11/2026 Approved MICHAEL ALLEN