923 5/8-3/4 W 54TH ST 90037
Certificate Information: 923 5/8-3/4 W 54TH ST 90037
- Application / Permit
- 24010-20000-02848
- Plan Check / Job No.
- B24VN09647
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New detached two story building with one ADU on first floor and another ADU on the second floor per STATE LAW
- Permit Issued
- Issued on 8/20/2024
- Issuing Office
- Current Status
- CofO Issued on 7/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | KHUONG TRUONG |
| Corrections Issued | 7/26/2024 | KHUONG TRUONG |
| Quality Review Completed | 7/30/2024 | GARO TELMI |
| Applicant returned to address corrections | 8/19/2024 | KHUONG TRUONG |
| Plan Check Approved | 8/20/2024 | KHUONG TRUONG |
| Issued | 8/20/2024 | APPLICANT |
| CofO in Progress | 7/7/2026 | SABAS ALONSO |
| CofO Issued | 7/9/2026 | DEROLD HAUFF |
| Permit Finaled | 7/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/7/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | CELINA MORENO |
| Sewer availability | Cleared | 8/8/2024 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 8/9/2024 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 10/29/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Partial Approval | BARRY HACHE |
| ELECTRICAL-Rough | 2/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 2/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 2/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Corrections Issued | SABAS ALONSO |
| Deputy Drilled-In Anchors | 4/4/2025 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 5/5/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 5/5/2025 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 5/5/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/5/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 5/20/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 5/20/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 6/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Interior/Exterior Lathing | 6/2/2025 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 6/2/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 6/4/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 6/4/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 6/11/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 6/11/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/11/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/18/2025 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 6/18/2025 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/1/2025 | Approved | SABAS ALONSO |
| Insulation | 8/6/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 8/14/2025 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 8/19/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 2/4/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 2/4/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 2/4/2026 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 2/4/2026 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 2/4/2026 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 2/4/2026 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 2/4/2026 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 6/12/2026 | Approved | SABAS ALONSO |
| Final | 6/12/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/12/2026 | Approved | SABAS ALONSO |
| HVAC-Final | 6/12/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 6/12/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/12/2026 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 6/12/2026 | Approved | SABAS ALONSO |
| Smoke Detectors | 6/12/2026 | Approved | SABAS ALONSO |
| Final | 6/22/2026 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/22/2026 | SGSOV Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/29/2026 | Approved | SABAS ALONSO |
| Final | 6/29/2026 | OK to Issue CofO | SABAS ALONSO |
| HVAC-Final | 6/29/2026 | Approved | SABAS ALONSO |