923 5/8-3/4 W 54TH ST 90037

Certificate Information: 923 5/8-3/4 W 54TH ST 90037

Application / Permit
24010-20000-02848
Plan Check / Job No.
B24VN09647
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New detached two story building with one ADU on first floor and another ADU on the second floor per STATE LAW
Permit Issued
Issued on 8/20/2024
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 KHUONG TRUONG
Corrections Issued 7/26/2024 KHUONG TRUONG
Quality Review Completed 7/30/2024 GARO TELMI
Applicant returned to address corrections 8/19/2024 KHUONG TRUONG
Plan Check Approved 8/20/2024 KHUONG TRUONG
Issued 8/20/2024 APPLICANT
CofO in Progress 7/7/2026 SABAS ALONSO
CofO Issued 7/9/2026 DEROLD HAUFF
Permit Finaled 7/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/7/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 8/7/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/8/2024 CELINA MORENO
Sewer availability Cleared 8/8/2024 CELINA MORENO
Tenant Habitability Plan Cleared 8/9/2024 HUGO GARRIDO GARZA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/23/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval SABAS ALONSO
Underground Mechanical 10/29/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Partial Approval BARRY HACHE
ELECTRICAL-Rough 2/4/2025 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 2/4/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 2/4/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Corrections Issued SABAS ALONSO
Deputy Drilled-In Anchors 4/4/2025 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 5/5/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Approved SABAS ALONSO
Green Building Rough 5/5/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 5/5/2025 Not Ready for Inspection SABAS ALONSO
Sewer 5/5/2025 Approved SABAS ALONSO
Underground Mechanical 5/5/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 5/20/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 5/20/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 6/2/2025 Not Ready for Inspection DAVID WILLIAMS
Interior/Exterior Lathing 6/2/2025 Partial Approval DAVID WILLIAMS
PLUMBING-Rough 6/2/2025 Approved DAVID WILLIAMS
Green Building Rough 6/4/2025 Not Ready for Inspection BARRY HACHE
HVAC-Rough 6/4/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 6/11/2025 Approved SABAS ALONSO
Green Building Rough 6/11/2025 Approved SABAS ALONSO
HVAC-Rough 6/11/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/18/2025 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 6/18/2025 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 8/1/2025 Approved SABAS ALONSO
Insulation 8/6/2025 Approved RONNIE MEDINA
Drywall Nailing 8/14/2025 Corrections Issued SABAS ALONSO
Drywall Nailing 8/19/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Approved SABAS ALONSO
ELECTRICAL-Final 2/4/2026 Not Ready for Inspection SABAS ALONSO
Final 2/4/2026 Corrections Issued SABAS ALONSO
Green Building Final 2/4/2026 Not Ready for Inspection SABAS ALONSO
HVAC-Final 2/4/2026 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 2/4/2026 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Not Ready SABAS ALONSO
Service/Power Release 2/4/2026 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 2/4/2026 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 6/12/2026 Approved SABAS ALONSO
Final 6/12/2026 Corrections Issued SABAS ALONSO
Green Building Final 6/12/2026 Approved SABAS ALONSO
HVAC-Final 6/12/2026 Approved SABAS ALONSO
PLUMBING-Final 6/12/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/12/2026 SGSOV Not Ready SABAS ALONSO
Service/Power Release 6/12/2026 Approved SABAS ALONSO
Smoke Detectors 6/12/2026 Approved SABAS ALONSO
Final 6/22/2026 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/22/2026 SGSOV Approved SABAS ALONSO
ELECTRICAL-Final 6/29/2026 Approved SABAS ALONSO
Final 6/29/2026 OK to Issue CofO SABAS ALONSO
HVAC-Final 6/29/2026 Approved SABAS ALONSO