472 1/4-1/2 E VERNON AVE 90011

Certificate Information: 472 1/4-1/2 E VERNON AVE 90011

Application / Permit
24010-20000-02847
Plan Check / Job No.
B24VN09636
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: New 2-Unit 2-Story Detached ADU per GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)(d) and (g)
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
Issued on 3/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/31/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 DAVID CASTILLO
Corrections Issued 8/20/2024 DAVID CASTILLO
Quality Review Completed 9/2/2024 KAVIAN REFAHI
Applicant returned to address corrections 1/27/2025 DAVID CASTILLO
Plan Check Approved 2/24/2025 DAVID CASTILLO
Issued 3/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/11/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 10/11/2024 CHRISTINA BRACO
Community Plan Implem. Overlay Cleared 11/12/2024 ANACANY HURTADO
Redevelopment Project Area Cleared 11/13/2024 YASMINE BASHIRI
Eng Process Fee Ord 176,300 Cleared 12/3/2024 CHRISTINA BRACO
Sewer availability Cleared 12/3/2024 CHRISTINA BRACO
Tenant Habitability Plan Cleared 2/10/2025 HUGO GARRIDO GARZA

Contact Information

Contractor La Rocca Builders Inc; Lic. No.: 934161-B 14320 VENTURA BLVD STE 724      SHERMAN OAKS, CA 91423
Engineer Manlangit,, Vicente; Lic. No.: C75499 20832 VALERIO ST UNIT 14      WINNETKA, CA 91306

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/24/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 5/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 5/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 6/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/6/2025 Corrections Issued MICHAEL LEWIS
HVAC-Rough 6/6/2025 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 6/6/2025 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 6/9/2025 Not Ready for Inspection BARRY HACHE
HVAC-Rough 6/9/2025 Approved BARRY HACHE
PLUMBING-Rough 6/9/2025 Approved BARRY HACHE
ELECTRICAL-Rough 6/10/2025 Corrections Issued JOHN QUINTANILLA
Green Building Rough 6/10/2025 Not Ready for Inspection JOHN QUINTANILLA
Verify Sprinkler Sign Off 6/10/2025 Approved JOHN QUINTANILLA
Insulation 6/17/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 6/20/2025 No Access for Inspection ENRIQUE MIRELES
Green Building Rough 6/20/2025 No Access for Inspection ENRIQUE MIRELES
Insulation 6/20/2025 No Access for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 6/25/2025 Approved JOHN QUINTANILLA
Green Building Rough 6/25/2025 Approved JOHN QUINTANILLA
Insulation 6/25/2025 Approved JOHN QUINTANILLA
Drywall Nailing 7/8/2025 Corrections Issued RONNIE MEDINA
Footing/Foundation/Slab 12/26/2025 No Access for Inspection SABAS ALONSO
Footing/Foundation/Slab 12/30/2025 Approved ALEJANDRO DE ARTOLA