10504 N DENSMORE AVE 91344
Certificate Information: 10504 N DENSMORE AVE 91344
- Application / Permit
- 24010-20000-02836
- Plan Check / Job No.
- B24VN09605
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW 2-STORY TYPE VB SFD PER SB9 ***13D Sprinkler required*** 1 of 2
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | KHUONG TRUONG |
| Corrections Issued | 8/1/2024 | KHUONG TRUONG |
| Quality Review Completed | 8/6/2024 | GARO TELMI |
| Plan Check Approved | 10/22/2024 | KHUONG TRUONG |
| Issued | 12/18/2024 | APPLICANT |
| CofO in Progress | 5/6/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 6/4/2026 | RUBEN SALAS |
| CofO Issued | 6/4/2026 | RUBEN SALAS |
| Permit Finaled | 6/4/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/3/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/5/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/8/2024 | RIDWAN HARDY |
| Senate Bill 9 | Cleared | 8/16/2024 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 10/17/2024 | JERRY KAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/9/2025 | Partial Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 1/9/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/20/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/20/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/9/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 4/9/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 4/16/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 6/2/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 6/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 6/5/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Wood Frame | 6/5/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/11/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/11/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/11/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/21/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/21/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/21/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/21/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/6/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 8/6/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 8/6/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 8/6/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 8/6/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 8/15/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 8/27/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/29/2025 | Approved | MICHAEL CORTEZ |
| Final | 4/20/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/20/2026 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/20/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 4/20/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/23/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 4/23/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 4/23/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/24/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/4/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 5/4/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 5/4/2026 | Approved | CHRISTOPHER ROJAS |