10504 N DENSMORE AVE 91344

Certificate Information: 10504 N DENSMORE AVE 91344

Application / Permit
24010-20000-02836
Plan Check / Job No.
B24VN09605
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: NEW 2-STORY TYPE VB SFD PER SB9 ***13D Sprinkler required*** 1 of 2
Permit Issued
Issued on 12/18/2024
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 KHUONG TRUONG
Corrections Issued 8/1/2024 KHUONG TRUONG
Quality Review Completed 8/6/2024 GARO TELMI
Plan Check Approved 10/22/2024 KHUONG TRUONG
Issued 12/18/2024 APPLICANT
CofO in Progress 5/6/2026 CHRISTOPHER ROJAS
Permit Finaled 6/4/2026 RUBEN SALAS
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/3/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/3/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/5/2024 CARLOS AGUILERA
Sewer availability Cleared 8/5/2024 CARLOS AGUILERA
Construction near power lines Cleared 8/8/2024 RIDWAN HARDY
Senate Bill 9 Cleared 8/16/2024 NATHAN ROMINE
Hydrant and Access approval Cleared 10/17/2024 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/9/2025 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 1/9/2025 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 1/9/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/20/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 2/20/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/20/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/9/2025 Corrections Issued CHRISTOPHER ROJAS
Wood Frame 4/9/2025 Partial Inspection CHRISTOPHER ROJAS
Wood Frame 4/16/2025 Partial Approval NICHOLAS TROWBRIDGE
Deputy Wood Construction 6/2/2025 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 6/5/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 6/5/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 6/5/2025 Corrections Issued NICHOLAS TROWBRIDGE
Wood Frame 6/5/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/11/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/11/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 6/11/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/11/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/21/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/21/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/21/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 7/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/6/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/6/2025 Approved CHRISTOPHER ROJAS
Insulation 8/6/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/6/2025 Partial Approval CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 8/6/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/15/2025 Approved CHRISTOPHER ROJAS
Shower Pan 8/27/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/17/2025 Partial Approval NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 9/29/2025 Approved MICHAEL CORTEZ
Final 4/20/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/20/2026 Approved JENNIFER RABUCHIN
Service/Power Release 4/20/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 4/20/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/23/2026 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 4/23/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 4/23/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/24/2026 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 5/4/2026 Approved CHRISTOPHER ROJAS
Final 5/4/2026 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 5/4/2026 Approved CHRISTOPHER ROJAS