17613 W SUNBURST ST 91325

Certificate Information: 17613 W SUNBURST ST 91325

Application / Permit
24010-20000-02806
Plan Check / Job No.
B24VN09458
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 11'-8" X 19' REC ROOM WITH ATTACHED 6' X 19' TRELLIS
Permit Issued
Issued on 11/19/2024
Issuing Office
Current Status
CofO Issued on 7/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 SELLA BENYAMIN
Corrections Issued 7/16/2024 SELLA BENYAMIN
Building Plans Picked Up 7/22/2024 APPLICANT
Quality Review Completed 11/19/2024 SELLA BENYAMIN
Plan Check Approved 11/19/2024 SELLA BENYAMIN
Issued 11/19/2024 APPLICANT
CofO in Progress 7/17/2025 NICHOLAS TROWBRIDGE
Permit Finaled 7/25/2025 RUBEN SALAS
CofO Issued 7/25/2025 RUBEN SALAS
Permit Finaled 7/25/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/2/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/21/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 8/22/2024 EDGAR ALCARAZ
Construction near power lines Cleared 11/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/27/2024 Partial Approval JAVIER RAMOS JR
Underground Mechanical 11/27/2024 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 12/12/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/12/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/14/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 1/14/2025 Approved JAVIER RAMOS JR
HVAC-Rough 1/14/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 1/14/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/15/2025 Partial Approval JAVIER RAMOS JR
Insulation 1/29/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/29/2025 Approved JAVIER RAMOS JR
Shower Pan 1/29/2025 Approved JAVIER RAMOS JR
Drywall Nailing 2/28/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 6/26/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Final 6/26/2025 Conditional Approval NICHOLAS TROWBRIDGE
Service/Power Release 6/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/16/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 7/16/2025 Approved NICHOLAS TROWBRIDGE
Final 7/16/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 7/16/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 7/16/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 7/16/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Service/Power Release 7/16/2025 Approved NICHOLAS TROWBRIDGE
Smoke Detectors 7/16/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 7/16/2025 Approved NICHOLAS TROWBRIDGE