17613 W SUNBURST ST 91325
Certificate Information: 17613 W SUNBURST ST 91325
- Application / Permit
- 24010-20000-02806
- Plan Check / Job No.
- B24VN09458
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 11'-8" X 19' REC ROOM WITH ATTACHED 6' X 19' TRELLIS
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- CofO Issued on 7/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | SELLA BENYAMIN |
| Corrections Issued | 7/16/2024 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/22/2024 | APPLICANT |
| Quality Review Completed | 11/19/2024 | SELLA BENYAMIN |
| Plan Check Approved | 11/19/2024 | SELLA BENYAMIN |
| Issued | 11/19/2024 | APPLICANT |
| CofO in Progress | 7/17/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 7/25/2025 | RUBEN SALAS |
| CofO Issued | 7/25/2025 | RUBEN SALAS |
| Permit Finaled | 7/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 8/2/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 11/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/27/2024 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 11/27/2024 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 12/12/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/12/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/14/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/14/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 1/14/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/14/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/15/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 1/29/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/29/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 1/29/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 2/28/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 6/26/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Final | 6/26/2025 | Conditional Approval | NICHOLAS TROWBRIDGE |
| Service/Power Release | 6/26/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 7/16/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Final | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 7/16/2025 | Approved | NICHOLAS TROWBRIDGE |