14273 W GREENLEAF ST 91423
Certificate Information: 14273 W GREENLEAF ST 91423
- Application / Permit
- 24010-20000-02805
- Plan Check / Job No.
- B24VN09456
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED 1-STORY (16'-0"x13'-9"), 193 SQFT PATIO COVER
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- Current Status
- Issued on 8/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | PETER MOSESIAN |
| Corrections Issued | 7/14/2024 | PETER MOSESIAN |
| Quality Review Completed | 7/17/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/23/2024 | APPLICANT |
| Plan Check Approved | 8/23/2024 | JASON HEALEY |
| Issued | 8/23/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/14/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2024 | TAL SHEMEN |
| Construction near power lines | Cleared | 7/23/2024 | JOSHUA MARTIN |
| ZA Case | Cleared | 7/24/2024 | DORIAN AGUILAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/31/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 1/7/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Partial Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/6/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 3/6/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Corrections Issued | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 4/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 4/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 4/8/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | MICHAEL CORTEZ |
| Verify Sprinkler Sign Off | 5/6/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 5/6/2025 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 5/14/2025 | Not Ready for Inspection | WILLIAM WREN |
| Drywall Nailing | 5/27/2025 | Partial Inspection | MISAEL ESPARZA |