434-434 1/2 E 47TH ST 90011
Certificate Information: 434-434 1/2 E 47TH ST 90011
- Application / Permit
- 24010-20000-02782
- Plan Check / Job No.
- B24VN09387
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: 2 NEW DETACHED ADU'S
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- Issued on 5/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 7/29/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/6/2024 | YOUNG KIM |
| Plan Check Approved | 5/7/2025 | ARSALAN SHABESTARI |
| Issued | 5/15/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/15/2024 | CELINA MORENO |
| Sewer availability | Cleared | 8/15/2024 | CELINA MORENO |
| Construction near power lines | Cleared | 4/21/2025 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 4/21/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2025 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 10/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 10/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/24/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 11/3/2025 | Approved | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 11/6/2025 | Approved | BARRY HACHE |
| Wood Frame | 12/15/2025 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |