434-434 1/2 E 47TH ST 90011

Certificate Information: 434-434 1/2 E 47TH ST 90011

Application / Permit
24010-20000-02782
Plan Check / Job No.
B24VN09387
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: 2 NEW DETACHED ADU'S
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
Issued on 5/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/10/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 ARSALAN SHABESTARI
Corrections Issued 7/29/2024 ARSALAN SHABESTARI
Quality Review Completed 8/6/2024 YOUNG KIM
Plan Check Approved 5/7/2025 ARSALAN SHABESTARI
Issued 5/15/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/15/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/15/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 8/15/2024 CELINA MORENO
Sewer availability Cleared 8/15/2024 CELINA MORENO
Construction near power lines Cleared 4/21/2025 ENRIQUE ACOSTA
Construction within easement Cleared 4/21/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2025 Approved MICHAEL LEWIS
Pre-Inspection 10/15/2025 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 10/22/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/24/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 11/3/2025 Approved LUIS CASTRO
Excavation/Setback/Form/Re-Bar 11/6/2025 Approved BARRY HACHE
Wood Frame 12/15/2025 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 2/10/2026 Corrections Issued ALEJANDRO DE ARTOLA