10823 1/2 W PENROSE ST 91352
Certificate Information: 10823 1/2 W PENROSE ST 91352
- Application / Permit
- 24010-20000-02753
- Plan Check / Job No.
- B24VN09307
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ATTACHED RECREATION ROOM ** ePlan**
- Permit Issued
- Issued on 8/21/2025
- Issuing Office
- Current Status
- Issued on 8/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/6/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/14/2024 | JASON HEALEY |
| Applicant returned to address corrections | 8/10/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/20/2025 | NILOOFAR MEHRAIN |
| Issued | 8/21/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 8/15/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 9/4/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/24/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 12/19/2024 | PATRICK PEREZ |
| Specific Plan | Cleared | 7/31/2025 | DORIAN AGUILAR |
| ZI | Cleared | 7/31/2025 | DORIAN AGUILAR |
| GPI Written Notices | Cleared | 8/11/2025 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 8/11/2025 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Raab,, Andres Gustavo; Lic. No.: C52713 | 13645 SHABLOW AVE SYLMAR, CA 91342 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/10/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 11/12/2025 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 11/13/2025 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/24/2025 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 1/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Special/Order Compliance | 1/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/18/2026 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 5/11/2026 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/10/2026 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 6/10/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/10/2026 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/15/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/15/2026 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/17/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/17/2026 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 6/17/2026 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/29/2026 | Approved | DAVID ANDERSON |
| Insulation | 6/29/2026 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/6/2026 | Approved | MATTHEW NELSON |