10214 N BRADLEY AVE 91331
Certificate Information: 10214 N BRADLEY AVE 91331
- Application / Permit
- 24010-20000-02721
- Plan Check / Job No.
- B24VN09187
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan:NEW 2 STORY SINGLE FAMILY RESIDENCE FIRE SPRINKLERED NFPA 13D THROUGH OUT TYPE VB CONSTRUCTION "COMPLY WITH DEPARTMENT ORDER effective date 01/19/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 3/27/2025
- Issuing Office
- Current Status
- Issued on 3/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | JAD BASMA |
| Corrections Issued | 8/4/2024 | JAD BASMA |
| Quality Review Completed | 8/8/2024 | GARO TELMI |
| Applicant returned to address corrections | 11/5/2024 | JAD BASMA |
| Applicant returned to address corrections | 3/18/2025 | JAD BASMA |
| Plan Check Approved | 3/20/2025 | JAD BASMA |
| Issued | 3/27/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/30/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/10/2025 | BIAINA HARITUNIAN |
| ZI | Cleared | 2/20/2025 | MATHEW QUAN |
| Hydrant and Access approval | Cleared | 3/13/2025 | JERRY KAO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/22/2025 | Corrections Issued | RAUL VASQUEZ |
| Excavation/Setback/Form/Re-Bar | 4/28/2025 | Corrections Issued | RAUL VASQUEZ |
| Pre-Inspection | 5/16/2025 | Corrections Issued | MARK VAN SLOOTEN |
| Excavation/Setback/Form/Re-Bar | 6/13/2025 | Approved | MARK VAN SLOOTEN |
| Footing/Foundation/Slab | 6/13/2025 | Approved | MARK VAN SLOOTEN |
| Deputy Reinf. Concrete | 6/17/2025 | Approved | MARK VAN SLOOTEN |
| BUILDING-Rough-Frame | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Final | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Green Building Final | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Green Building Rough | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| PLUMBING-Rough | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/9/2025 | SGSOV Not Ready | RAUL VASQUEZ |
| Service/Power Release | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Smoke Detectors | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Verify Sprinkler Sign Off | 7/9/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| PLUMBING-Rough | 7/15/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Underground Mechanical | 7/17/2025 | Approved | RAUL VASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | No Access for Inspection | MARIO CUEVAS |
| Insulation | 8/11/2025 | No Access for Inspection | MARIO CUEVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Approved | MARK VAN SLOOTEN |
| Insulation | 8/13/2025 | Corrections Issued | MARK VAN SLOOTEN |
| BUILDING-Rough-Frame | 10/24/2025 | Corrections Issued | RAUL VASQUEZ |
| Green Building Rough | 10/24/2025 | Approved | RAUL VASQUEZ |
| Verify Sprinkler Sign Off | 10/24/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 10/28/2025 | Partial Approval | RAUL VASQUEZ |
| ELECTRICAL-Rough | 11/17/2025 | Approved | RAUL VASQUEZ |
| PLUMBING-Rough | 11/17/2025 | Approved | RAUL VASQUEZ |
| HVAC-Rough | 12/31/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Interior/Exterior Lathing | 12/31/2025 | Approved | RAUL VASQUEZ |
| Verify Sprinkler Sign Off | 12/31/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| HVAC-Rough | 1/29/2026 | Corrections Issued | RAUL VASQUEZ |
| Insulation | 1/29/2026 | Not Ready for Inspection | RAUL VASQUEZ |
| Insulation | 2/6/2026 | Not Ready for Inspection | MARIO CUEVAS |
| Insulation | 2/10/2026 | Approved | RAUL VASQUEZ |
| Drywall Nailing | 3/12/2026 | Approved | RAUL VASQUEZ |
| Sewer | 3/12/2026 | Approved | RAUL VASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2026 | Corrections Issued | RAUL VASQUEZ |
| Shower Pan | 4/30/2026 | Approved | RAUL VASQUEZ |