208 1/4-3/4 E 84TH ST 90003
Certificate Information: 208 1/4-3/4 E 84TH ST 90003
- Application / Permit
- 24010-20000-02706
- Plan Check / Job No.
- B24VN09138
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New two detached ADUs per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 3/18/2025
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2024 | ALEXANDER JOO |
| Corrections Issued | 9/24/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 11/15/2024 | ALEXANDER JOO |
| Plan Check Approved | 1/8/2025 | CARLOS MONTES |
| Issued | 3/18/2025 | APPLICANT |
| CofO in Progress | 4/1/2026 | JOHN QUINTANILLA |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
| CofO Issued | 4/2/2026 | DEROLD HAUFF |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2024 | CHRISTINA BRACO |
| Highway dedication | Cleared | 10/17/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 11/13/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 11/21/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Neeraj Mittal; Lic. No.: 1127454-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/26/2025 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/2/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 4/7/2025 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 4/9/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 5/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 5/21/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 5/21/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 5/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 6/6/2025 | Partial Approval | ANTHONY RAMOS |
| Green Building Rough | 6/23/2025 | Approved | LUIS CASTRO |
| Wood Frame | 6/23/2025 | Partial Approval | LUIS CASTRO |
| Wood Frame | 6/26/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 7/11/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 7/22/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 7/22/2025 | Approved | ALEX COLIN |
| Final | 12/12/2025 | Conditional Approval | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 12/12/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 12/12/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 12/12/2025 | Approved | JOHN QUINTANILLA |
| Final | 12/23/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 3/4/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 3/9/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 3/16/2026 | OK to Issue CofO | JOHN QUINTANILLA |