6950 W BECKETT ST 91042

Certificate Information: 6950 W BECKETT ST 91042

Application / Permit
24010-20000-02703
Plan Check / Job No.
B24VN09121
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
EPLAN: NEW 2-STORY IRREGUALR SHAPED 33'-2" x 33'-1 15/16" S.F.D. WITH ATTACHED GARAGE AND TRELLIS PER ENGINEERING. FIRE SPRINKLER NFPA-13D THRU-OUT
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
CofO Issued on 9/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 ALFRED RAMIREZ
Corrections Issued 7/10/2024 ALFRED RAMIREZ
Quality Review Completed 7/12/2024 STEVEN KIM
Applicant returned to address corrections 8/15/2024 ALFRED RAMIREZ
Applicant returned to address corrections 9/18/2024 ALFRED RAMIREZ
Applicant returned to address corrections 10/1/2024 ALFRED RAMIREZ
Plan Check Approved 10/17/2024 ALFRED RAMIREZ
Plan Check Approved 10/17/2024 ALFRED RAMIREZ
Issued 10/17/2024 APPLICANT
CofO in Progress 9/10/2025 WILLIAM WREN
Permit Finaled 9/19/2025 RUBEN SALAS
CofO Issued 9/19/2025 RUBEN SALAS
Permit Finaled 9/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/13/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/13/2024 EDGAR ALCARAZ
Disturb/Remove Protected Trees Cleared 9/10/2024 ADALBERTO VERA
Trees in Parkway Cleared 9/10/2024 ADALBERTO VERA
Permit Cleared 9/13/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/30/2024 PATRICK PEREZ
GPI Written Notices Cleared 10/1/2024 ALFRED RAMIREZ
Grading Pre-Inspection Cleared 10/1/2024 CHARLES POWELL
Private sewage disp. approval Cleared 10/15/2024 MICHAEL TEMPLE

Contact Information

Architect Ben, David, Yohai; Lic. No.: NA39255       ,
Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/7/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 11/7/2024 Corrections Issued WILLIAM WREN
Excavation/Setback/Form/Re-Bar 11/14/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 11/14/2024 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 11/25/2024 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 12/2/2024 Approved WILLIAM WREN
Deputy Reinf. Concrete 12/4/2024 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 1/30/2025 Conditional Approval RAUL OLAGI
Deputy Wood Construction 1/30/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued WILLIAM WREN
Wood Frame 1/30/2025 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 2/3/2025 Partial Approval KEVIN BERBERYAN
Green Building Rough 2/3/2025 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 2/3/2025 Partial Inspection KEVIN BERBERYAN
Special/Order Compliance 2/4/2025 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 3/7/2025 Approved WILLIAM WREN
HVAC-Rough 3/7/2025 Approved WILLIAM WREN
PLUMBING-Rough 3/7/2025 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 3/21/2025 Approved WILLIAM WREN
ELECTRICAL-Final 6/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
Service/Power Release 6/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Final 6/5/2025 Approved WILLIAM WREN
Service/Power Release 6/5/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/6/2025 Approved WILLIAM WREN
Drywall Nailing 8/6/2025 Approved WILLIAM WREN
Final 8/6/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 8/6/2025 Approved WILLIAM WREN
Green Building Final 8/6/2025 Approved WILLIAM WREN
Green Building Rough 8/6/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 8/6/2025 SGSOV Not Required WILLIAM WREN
Smoke Detectors 8/6/2025 Approved WILLIAM WREN
Final 9/5/2025 OK to Issue CofO WILLIAM WREN