10415 N LEMONA AVE 91345
Certificate Information: 10415 N LEMONA AVE 91345
- Application / Permit
- 24010-20000-02694
- Plan Check / Job No.
- B24VN09100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING (34'-0"x19'-6"), 1193 SQFT PER SB9 W/NFPA 13D SPRINKLERS THROUGHOUT. ALL ELECTRIC BUILDING
- Permit Issued
- Issued on 11/26/2024
- Issuing Office
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | PETER MOSESIAN |
| Corrections Issued | 6/30/2024 | PETER MOSESIAN |
| Quality Review Completed | 7/3/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/5/2024 | APPLICANT |
| Plan Check Approved | 11/26/2024 | PETER MOSESIAN |
| Issued | 11/26/2024 | APPLICANT |
| CofO in Progress | 5/8/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 5/27/2025 | RUBEN SALAS |
| CofO Issued | 5/27/2025 | RUBEN SALAS |
| Permit Finaled | 5/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/9/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/9/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 8/29/2024 | ALEX VELA |
| Hydrant and Access approval | Cleared | 8/30/2024 | LAVEON RIDER |
| Construction near power lines | Cleared | 11/20/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 1015 VISTA GRANDE ST BURBANK, CA 91501 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/16/2024 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/18/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Corrections Issued | ROBERT GOLD |
| Deputy Wood Construction | 1/3/2025 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 1/15/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/15/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/24/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 2/25/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 3/4/2025 | Conditional Approval | LOUIS ESCOTO |
| Insulation | 3/4/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 3/4/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/6/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/6/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/6/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 5/6/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2025 | SGSOV Not Required | JENNIFER RABUCHIN |
| Service/Power Release | 5/6/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/6/2025 | Approved | JENNIFER RABUCHIN |