10120 N LAUREL CANYON BLVD 91331

Certificate Information: 10120 N LAUREL CANYON BLVD 91331

Application / Permit
24010-20000-02658
Plan Check / Job No.
B24VN08960
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 24' X 50' 1 STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 9/22/2024
Issuing Office
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 SELLA BENYAMIN
Corrections Issued 7/18/2024 SELLA BENYAMIN
Quality Review Completed 7/24/2024 STEVEN KIM
Applicant returned to address corrections 8/1/2024 SELLA BENYAMIN
Plan Check Approved 9/13/2024 SELLA BENYAMIN
Issued 9/22/2024 APPLICANT
CofO in Progress 2/19/2026 MICHEL ABAJAN
Permit Finaled 3/10/2026 RUBEN SALAS
CofO Issued 3/10/2026 RUBEN SALAS
Permit Finaled 3/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/25/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/25/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/25/2024 EDGAR ALCARAZ
Sewer availability Cleared 7/25/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/15/2025 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 1/16/2025 Conditional Approval ROBERT GOLD
Pre-Inspection 1/29/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 4/8/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/8/2025 Approved MICHEL ABAJAN
HVAC-Rough 4/8/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 4/8/2025 Corrections Issued MICHEL ABAJAN
Verify Sprinkler Sign Off 4/8/2025 Approved MICHEL ABAJAN
Insulation 4/18/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/18/2025 Approved MICHEL ABAJAN
Drywall Nailing 4/30/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/15/2025 Approved MICHEL ABAJAN
Final 8/15/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 8/15/2025 Approved MICHEL ABAJAN
PLUMBING-Final 8/15/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 8/15/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/15/2025 Approved MICHEL ABAJAN
Final 12/11/2025 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 12/11/2025 Not Ready for Inspection MICHEL ABAJAN
Final 2/18/2026 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 2/18/2026 Approved MICHEL ABAJAN