977-977 1/2 W 46TH ST 90037

Certificate Information: 977-977 1/2 W 46TH ST 90037

Application / Permit
24010-20000-02643
Plan Check / Job No.
B24VN08888
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW TWO 2-STORY 20'-4 1/2" x 42'-0" DETACHED ACCESSORY DWELLING UNITS TO COMPLY WITH CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) PER ENGINEERING. **SEE COMMENTS**
Permit Issued
Issued on 2/13/2026
Issuing Office
Current Status
Issued on 2/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 ALFRED RAMIREZ
Corrections Issued 8/3/2024 ALFRED RAMIREZ
Quality Review Completed 8/6/2024 STEVEN KIM
Plan Check Approved 12/13/2024 ALFRED RAMIREZ
Issued 2/13/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/7/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/8/2024 TREVOR QUAN
Sewer availability Cleared 8/8/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/13/2024 AMBER CAMPBELL
Community Plan Implem. Overlay Cleared 9/19/2024 MANERI ROMAN
ZI Cleared 9/19/2024 MANERI ROMAN
Historic Resource Verification Cleared 11/27/2024 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 11/27/2024 ELIZABETH GALLARDO
ZI Cleared 11/27/2024 ELIZABETH GALLARDO

Contact Information

Contractor Custom Pro Tile & Stone Inc; Lic. No.: 987695-B       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2026 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 2/18/2026 Partial Approval BARRY HACHE
Excavation/Setback/Form/Re-Bar 2/24/2026 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 2/25/2026 Corrections Issued BARRY HACHE
Excavation/Setback/Form/Re-Bar 2/26/2026 Approved RAUL BARAJAS
Footing/Foundation/Slab 2/26/2026 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 3/25/2026 Not Ready for Inspection BARRY HACHE
HVAC-Rough 3/25/2026 Corrections Issued BARRY HACHE
PLUMBING-Rough 3/25/2026 Corrections Issued BARRY HACHE
Sewer 3/25/2026 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 3/27/2026 Not Ready for Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 3/27/2026 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 3/27/2026 Not Ready for Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 4/1/2026 Partial Approval RAUL BARAJAS
Wood Frame 4/1/2026 Partial Approval RAUL BARAJAS
Insulation 4/6/2026 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 4/6/2026 Not Ready for Inspection RAUL BARAJAS
Drywall Nailing 4/27/2026 Partial Approval ALEX COLIN
Shower Pan 5/4/2026 Partial Approval ALEX COLIN
Interior/Exterior Lathing 5/7/2026 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/17/2026 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 6/17/2026 Partial Approval RAUL BARAJAS
HVAC-Rough 6/17/2026 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 6/17/2026 Partial Approval RAUL BARAJAS
PLUMBING-Rough 6/17/2026 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 6/17/2026 Partial Inspection RAUL BARAJAS
Wood Frame 6/17/2026 Partial Approval RAUL BARAJAS
Insulation 6/25/2026 Approved BARRY HACHE
Deputy Wood Construction 6/30/2026 Conditional Approval BARRY HACHE
Drywall Nailing 6/30/2026 Partial Approval BARRY HACHE
Interior/Exterior Lathing 7/9/2026 Approved BARRY HACHE
Shower Pan 7/9/2026 Approved BARRY HACHE