20339 W ACRE ST 91306
Certificate Information: 20339 W ACRE ST 91306
- Application / Permit
- 24010-20000-02630
- Plan Check / Job No.
- B24VN08813
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 803 ft detached Accessory Dwelling Unit (ADU)
- Permit Issued
- Issued on 11/6/2024
- Issuing Office
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | JOSEPH RAFOLS |
| Corrections Issued | 6/28/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 11/5/2024 | JOSEPH RAFOLS |
| Issued | 11/6/2024 | APPLICANT |
| CofO in Progress | 9/8/2025 | JEFFREY HARTLINE |
| Permit Finaled | 9/19/2025 | JOHN JANSON |
| CofO Issued | 9/19/2025 | JOHN JANSON |
| Permit Finaled | 9/19/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 6/28/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 6/28/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 11/1/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 11/1/2024 | TINA MIRANDA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Ha My Design, Inc; Lic. No.: 999603-B | , |
| Engineer | Kim,, Kevin Chae; Lic. No.: C53821 | 6099 PEREGRINE DR. JURUPA VALLEY, CA 91752 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/18/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 11/18/2024 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 11/26/2024 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 11/26/2024 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 12/26/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 12/26/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 12/26/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 12/26/2024 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 12/26/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 1/6/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 1/6/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 1/6/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 1/13/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 1/13/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/13/2025 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 1/13/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 1/17/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/17/2025 | Partial Approval | JEFFREY HARTLINE |
| Drywall Nailing | 1/31/2025 | Approved | JEFFREY HARTLINE |
| Sewer | 4/1/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Sewer | 4/7/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 5/19/2025 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 5/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 5/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 5/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 5/19/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Required | JEFFREY HARTLINE |
| Service/Power Release | 5/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 5/19/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 8/28/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 8/28/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 8/28/2025 | Approved | JEFFREY HARTLINE |
| Green Building Final | 8/28/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 8/28/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 8/28/2025 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 8/28/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 9/2/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 9/2/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 9/2/2025 | Approved | JEFFREY HARTLINE |
| Final | 9/8/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 9/8/2025 | Approved | JEFFREY HARTLINE |