13847 W EUSTACE ST 91331

Certificate Information: 13847 W EUSTACE ST 91331

Application / Permit
24010-20000-02607
Plan Check / Job No.
B24VN08748
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN (N) DETACHED ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 10/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2024 APPLICANT
Assigned to Plan Check Engineer 6/26/2024 MINA HABILI
Corrections Issued 6/27/2024 MINA HABILI
Applicant returned to address corrections 12/31/2024 SAMUEL GONZALEZ
Applicant returned to address corrections 2/7/2025 MINA HABILI
Plan Check Approved 2/12/2025 MINA HABILI
Issued 3/12/2025 APPLICANT
CofO in Progress 9/29/2025 JENNIFER RABUCHIN
Permit Finaled 10/3/2025 RUBEN SALAS
CofO Issued 10/3/2025 RUBEN SALAS
Permit Finaled 10/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/3/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/3/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/14/2024 CARLOS AGUILERA
Sewer availability Cleared 8/14/2024 CARLOS AGUILERA
Construction near power lines Cleared 11/22/2024 RIDWAN HARDY
ZI Cleared 12/26/2024 ALEX VELA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/30/2025 Conditional Approval MICHEL ABAJAN
PLUMBING-Rough 5/8/2025 Partial Approval MICHEL ABAJAN
Wood Frame 5/8/2025 Partial Approval MICHEL ABAJAN
Insulation 5/12/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Partial Approval MICHEL ABAJAN
Underground Mechanical 5/13/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 6/25/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 6/25/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/7/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/7/2025 Approved MICHEL ABAJAN
Green Building Rough 7/7/2025 Approved MICHEL ABAJAN
HVAC-Rough 7/7/2025 Approved MICHEL ABAJAN
MERV13>=Rough 7/7/2025 Approved MICHEL ABAJAN
METHANE-Rough 7/7/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/7/2025 Approved MICHEL ABAJAN
Insulation 7/10/2025 Corrections Issued LOUIS ESCOTO
Drywall Nailing 7/22/2025 Approved MICHEL ABAJAN
Shower Pan 8/14/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 8/19/2025 Approved MICHEL ABAJAN
Final 9/18/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 9/18/2025 Partial Approval KEVIN BERBERYAN
Green Building Final 9/18/2025 Approved KEVIN BERBERYAN
MERV13>=Final 9/18/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 9/18/2025 Approved KEVIN BERBERYAN
Smoke Detectors 9/18/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 9/25/2025 Approved JENNIFER RABUCHIN
Final 9/25/2025 OK to Issue CofO JENNIFER RABUCHIN
Footing/Foundation/Slab 9/25/2025 Approved JENNIFER RABUCHIN
Green Building Final 9/25/2025 Approved JENNIFER RABUCHIN
HVAC-Final 9/25/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/25/2025 Approved JENNIFER RABUCHIN