13847 W EUSTACE ST 91331
Certificate Information: 13847 W EUSTACE ST 91331
- Application / Permit
- 24010-20000-02607
- Plan Check / Job No.
- B24VN08748
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN (N) DETACHED ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/12/2025
- Issuing Office
- Current Status
- CofO Issued on 10/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2024 | MINA HABILI |
| Corrections Issued | 6/27/2024 | MINA HABILI |
| Applicant returned to address corrections | 12/31/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 2/7/2025 | MINA HABILI |
| Plan Check Approved | 2/12/2025 | MINA HABILI |
| Issued | 3/12/2025 | APPLICANT |
| CofO in Progress | 9/29/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 10/3/2025 | RUBEN SALAS |
| CofO Issued | 10/3/2025 | RUBEN SALAS |
| Permit Finaled | 10/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/3/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/14/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/22/2024 | RIDWAN HARDY |
| ZI | Cleared | 12/26/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/30/2025 | Conditional Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 5/8/2025 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 5/8/2025 | Partial Approval | MICHEL ABAJAN |
| Insulation | 5/12/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 5/13/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/25/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/25/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/7/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/7/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/7/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/7/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/7/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/7/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/7/2025 | Approved | MICHEL ABAJAN |
| Insulation | 7/10/2025 | Corrections Issued | LOUIS ESCOTO |
| Drywall Nailing | 7/22/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 8/14/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/19/2025 | Approved | MICHEL ABAJAN |
| Final | 9/18/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/18/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Final | 9/18/2025 | Approved | KEVIN BERBERYAN |
| MERV13>=Final | 9/18/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Service/Power Release | 9/18/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/18/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 9/25/2025 | Approved | JENNIFER RABUCHIN |
| Final | 9/25/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/25/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 9/25/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/25/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/25/2025 | Approved | JENNIFER RABUCHIN |