13154 N VAUGHN ST 91331
Certificate Information: 13154 N VAUGHN ST 91331
- Application / Permit
- 24010-20000-02562
- Plan Check / Job No.
- B24VN08549
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ALL-ELECTRIC ONE-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 7/24/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 6/22/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/2/2024 | APPLICANT |
| Plan Check Approved | 7/24/2024 | ROSENDO MEDINA |
| Issued | 7/24/2024 | APPLICANT |
| CofO in Progress | 7/17/2025 | MICHEL ABAJAN |
| CofO in Progress | 8/20/2025 | MICHEL ABAJAN |
| CofO in Progress | 9/5/2025 | MICHEL ABAJAN |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/24/2024 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 6/25/2024 | ASHLEY RODARTE |
| Sewer availability | Cleared | 6/26/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/4/2025 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 2/12/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/12/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/12/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/25/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/25/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/25/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 2/25/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/25/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/25/2025 | Approved | MICHEL ABAJAN |
| Insulation | 2/27/2025 | Conditional Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/27/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/3/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/14/2025 | Approved | MICHEL ABAJAN |
| Final | 4/14/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/14/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/14/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 4/14/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/14/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 4/14/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 4/14/2025 | Approved | MICHEL ABAJAN |
| Final | 7/9/2025 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 7/9/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/16/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 7/16/2025 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 8/8/2025 | Partial Inspection | MICHEL ABAJAN |