20235 W HARTLAND ST 91306

Certificate Information: 20235 W HARTLAND ST 91306

Application / Permit
24010-20000-02559
Plan Check / Job No.
B24VN08533
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 30' X 26'-10" TWO STORY IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/4/2025
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 SELLA BENYAMIN
Corrections Issued 7/11/2024 SELLA BENYAMIN
Quality Review Completed 7/12/2024 STEVEN KIM
Applicant returned to address corrections 8/1/2024 SELLA BENYAMIN
Applicant returned to address corrections 12/10/2024 SELLA BENYAMIN
Plan Check Approved 12/13/2024 SELLA BENYAMIN
No Progress 1/2/2025 SELLA BENYAMIN
Plan Check Approved 1/2/2025 SELLA BENYAMIN
Issued 1/4/2025 APPLICANT
CofO in Progress 9/15/2025 ALEXANDER HANDY
No Progress 11/17/2025 ROBERT GOLD
CofO in Progress 11/17/2025 ROBERT GOLD
CofO in Progress 1/12/2026 ALEXANDER HANDY
Permit Finaled 2/20/2026 JOHN JANSON
CofO Issued 2/20/2026 JOHN JANSON
Permit Finaled 2/20/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/16/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/16/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/25/2024 EDGAR ALCARAZ
Sewer availability Cleared 7/25/2024 EDGAR ALCARAZ
Construction near power lines Cleared 11/21/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2025 Partial Approval JUAN ALVARADO
PLUMBING-Rough 1/24/2025 Partial Approval JUAN ALVARADO
Special/Order Compliance 1/24/2025 Partial Inspection SEAN WIRCH
Excavation/Setback/Form/Re-Bar 1/31/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 1/31/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 2/6/2025 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 2/6/2025 Not Ready for Inspection ALEXANDER HANDY
Sewer 2/6/2025 Not Ready for Inspection ALEXANDER HANDY
Verify Sprinkler Sign Off 2/6/2025 Not Ready for Inspection ALEXANDER HANDY
Wood Frame 2/6/2025 Not Ready for Inspection ALEXANDER HANDY
Deputy Wood Construction 2/20/2025 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 4/22/2025 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 4/22/2025 Approved ALEXANDER HANDY
Green Building Rough 4/22/2025 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 4/22/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 4/22/2025 Corrections Issued ALEXANDER HANDY
Verify Sprinkler Sign Off 4/22/2025 Not Ready for Inspection ALEXANDER HANDY
Wood Frame 4/22/2025 Partial Approval ALEXANDER HANDY
Interior/Exterior Lathing 4/25/2025 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 4/25/2025 Approved ALEXANDER HANDY
Shower Pan 4/25/2025 Approved ALEXANDER HANDY
Wood Frame 4/25/2025 Approved ALEXANDER HANDY
Insulation 5/2/2025 Approved ALEXANDER HANDY
Drywall Nailing 5/8/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 5/21/2025 Approved ALEXANDER HANDY
Service/Power Release 5/22/2025 Not Ready for Inspection ALEXANDER HANDY
Service/Power Release 6/11/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 7/22/2025 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Final 7/22/2025 Not Ready for Inspection ALEXANDER HANDY
Final 7/22/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 7/22/2025 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 7/22/2025 Approved ALEXANDER HANDY
HVAC-Final 7/22/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Final 7/22/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 7/22/2025 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 7/22/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 8/18/2025 No Access for Inspection ALEXANDER HANDY
Final 8/18/2025 No Access for Inspection ALEXANDER HANDY
Green Building Final 8/18/2025 No Access for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 8/18/2025 No Access for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 8/20/2025 Not Ready for Inspection ALEXANDER HANDY
Final 8/20/2025 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 8/20/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 8/20/2025 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 9/12/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 9/12/2025 Approved ALEXANDER HANDY
Final 9/12/2025 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 9/12/2025 Approved ALEXANDER HANDY
PLUMBING-Final 9/12/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV No Gas ALEXANDER HANDY
Service/Power Release 9/12/2025 Approved ALEXANDER HANDY
Final 1/7/2026 OK to Issue CofO ALEXANDER HANDY