8619 N HATILLO AVE 91306
Certificate Information: 8619 N HATILLO AVE 91306
- Application / Permit
- 24010-20000-02550
- Plan Check / Job No.
- B24VN08502
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan NEW DETACHED 2 STORY SB9 UNIT per SB9 Two-Unit Development Ca Govt Code 65852.21. FIRE SPRINKLER NFPA-13D THORUGHOUT.
- Permit Issued
- Issued on 3/18/2025
- Issuing Office
- Current Status
- Issued on 3/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2024 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/25/2024 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 7/15/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 9/12/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/18/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/6/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/14/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/18/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/20/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 11/22/2024 | FARSHAD ALIMOHAMADI |
| Issued | 3/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/2/2024 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 8/13/2024 | ALEX VELA |
| Construction near power lines | Cleared | 8/20/2024 | THERESA NGUYEN |
| Low Impact Development (LID) | Cleared | 9/5/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/9/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/10/2024 | PATRICK PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 5/19/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 5/19/2025 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 6/4/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 9/9/2025 | Partial Approval | SCOTT SOBEL |
| ELECTRICAL-Rough | 9/30/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 9/30/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | JEFFREY HARTLINE |
| Gas Test | 10/23/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Rough | 10/23/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Special/Order Compliance | 10/23/2025 | Corrections Issued | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 10/23/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 12/22/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 12/22/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/22/2025 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 1/13/2026 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/22/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/22/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/23/2026 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 2/23/2026 | Approved | JEFFREY HARTLINE |