4115 N FULTON AVE 91423
Certificate Information: 4115 N FULTON AVE 91423
- Application / Permit
- 24010-20000-02524
- Plan Check / Job No.
- B24VN08391
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 49'4"X 48' TWO STORY SFD WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- CofO in Progress on 5/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | RARES BODEA |
| Corrections Issued | 6/24/2024 | RARES BODEA |
| Quality Review Completed | 6/28/2024 | STEVEN KIM |
| Building Plans Picked Up | 6/28/2024 | APPLICANT |
| Applicant returned to address corrections | 10/4/2024 | RARES BODEA |
| Applicant returned to address corrections | 11/1/2024 | RARES BODEA |
| Applicant returned to address corrections | 11/15/2024 | RARES BODEA |
| Plan Check Approved | 11/19/2024 | RARES BODEA |
| Issued | 11/19/2024 | APPLICANT |
| CofO in Progress | 5/12/2026 | CHRISTOPHE COCHRAN |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 7/5/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/31/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 9/16/2024 | GILBERT URREA |
| GPI Written Notices | Cleared | 10/4/2024 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 10/4/2024 | RARES BODEA |
| Trees in Parkway | Cleared | 10/21/2024 | MIGUEL ORNELAS |
| Permit | Cleared | 11/1/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/24/2024 | Corrections Issued | RAUL OLAGI |
| Sewer | 12/24/2024 | Not Ready for Inspection | RAUL OLAGI |
| Special/Order Compliance | 12/26/2024 | Corrections Issued | RAUL OLAGI |
| Deputy Reinf. Concrete | 12/30/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 1/2/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/2/2025 | Approved | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 1/6/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 1/13/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/25/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| HVAC-Rough | 2/25/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 2/25/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 3/21/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/21/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 3/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 3/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 6/18/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/10/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 8/27/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 9/15/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 3/6/2026 | Partial Inspection | MISAEL ESPARZA |
| HVAC-Final | 3/6/2026 | Partial Inspection | MISAEL ESPARZA |
| Final | 4/23/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 4/23/2026 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2026 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 4/23/2026 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/23/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/29/2026 | OK to Issue CofO | CHRISTOPHE COCHRAN |