14883 W BLEDSOE ST 91342

Certificate Information: 14883 W BLEDSOE ST 91342

Application / Permit
24010-20000-02509
Plan Check / Job No.
B24VN08346
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d) an (g). Design per licensed engineer.
Permit Issued
Issued on 11/12/2024
Issuing Office
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2024 APPLICANT
Assigned to Plan Check Engineer 6/18/2024 CAROLEAN BASMA
Corrections Issued 6/20/2024 CAROLEAN BASMA
Applicant returned to address corrections 9/11/2024 CAROLEAN BASMA
Plan Check Approved 10/30/2024 CAROLEAN BASMA
Issued 11/12/2024 APPLICANT
CofO in Progress 2/10/2026 KIRK SANDERS
CofO Issued 3/24/2026 RUBEN SALAS
Permit Finaled 3/24/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/29/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/29/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/29/2024 CARLOS AGUILERA
Sewer availability Cleared 7/30/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Aranda,, Xochitl; Lic. No.: C71066 143 CLAIREMONT DR      EL PASO, TX 79912
Engineer Aranda,, Xochitl; Lic. No.: NA71066       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/25/2025 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 3/27/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/22/2025 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 5/22/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 5/22/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 5/22/2025 Approved KEVIN BERBERYAN
Sewer 6/26/2025 Approved KEVIN BERBERYAN
Wood Frame 6/26/2025 Partial Approval KEVIN BERBERYAN
Insulation 7/1/2025 Approved MICHAEL CORTEZ
Drywall Nailing 7/25/2025 Approved KEVIN BERBERYAN
Green Building Rough 7/25/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/8/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/4/2025 Corrections Issued KEVIN BERBERYAN
Underground Mechanical 9/4/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/10/2025 Approved KEVIN BERBERYAN
Final 10/10/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 10/10/2025 Approved KEVIN BERBERYAN
Green Building Final 10/10/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 10/10/2025 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 10/10/2025 Approved KEVIN BERBERYAN
Final 2/9/2026 OK to Issue CofO KIRK SANDERS
Footing/Foundation/Slab 2/9/2026 Approved KIRK SANDERS
Service/Power Release 2/9/2026 Approved KIRK SANDERS
Special/Order Compliance 2/9/2026 Not Ready for Inspection KIRK SANDERS