14811-14813 W MCCORMICK ST 91411

Certificate Information: 14811-14813 W MCCORMICK ST 91411

Application / Permit
24010-20000-02508
Plan Check / Job No.
B24VN08344
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-Story (88.3' x 59' Irregular Shape) Single Family Dwelling with attached garage, trellis patio cover and Accessory Dwelling Unit per LAMC 12.22 A.33 (c) and (e). NFPA 13D Fire Sprinklers Throughout.
Permit Issued
Issued on 11/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 VAHAN JIVALAGIAN
Corrections Issued 6/28/2024 VAHAN JIVALAGIAN
Quality Review Completed 7/10/2024 OMID HEDAYAT
Building Plans Picked Up 7/16/2024 APPLICANT
Applicant returned to address corrections 11/14/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/20/2024 VAHAN JIVALAGIAN
Issued 11/20/2024 APPLICANT
CofO in Progress 6/3/2026 RAUL OLAGI
CofO Issued 6/9/2026 RUBEN SALAS
Permit Finaled 6/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/29/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/29/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/30/2024 EDGAR ALCARAZ
Trees in Parkway Cleared 8/26/2024 ADALBERTO VERA
Construction near power lines Cleared 9/5/2024 RIDWAN HARDY
Miscellaneous Cleared 9/26/2024 DORIAN AGUILAR
Hydrant and Access approval Cleared 10/17/2024 KURT CORRAL
Permit Cleared 11/14/2024 CARLOS AGUILERA
Sewer availability Cleared 11/14/2024 CARLOS AGUILERA

Contact Information

Contractor Urban Culture Design & Development; Lic. No.: 1126457-B 2219 W OLIVE   #306    BURBANK, CA 91506
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/13/2025 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 1/17/2025 Approved JACK KARGODORIAN
Footing/Foundation/Slab 1/17/2025 Partial Approval JACK KARGODORIAN
Deputy Reinf. Concrete 1/24/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/28/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Partial Approval JACK KARGODORIAN
Wood Frame 4/22/2025 Corrections Issued JACK KARGODORIAN
Underground Mechanical 5/8/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Approved JACK KARGODORIAN
HVAC-Rough 5/13/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 5/13/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 5/22/2025 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 5/22/2025 Approved JACK KARGODORIAN
Green Building Rough 5/22/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 5/22/2025 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 5/22/2025 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 6/4/2025 Partial Approval JACK KARGODORIAN
Insulation 6/11/2025 Corrections Issued JACK KARGODORIAN
Shower Pan 6/11/2025 Approved JACK KARGODORIAN
Insulation 6/23/2025 Partial Inspection JACK KARGODORIAN
Drywall Nailing 6/30/2025 Approved JACK KARGODORIAN
Insulation 6/30/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 8/5/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 12/22/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 12/24/2025 Approved CRAIG DAVIS
HVAC-Final 12/24/2025 Approved CRAIG DAVIS
BUILDING-Rough-Frame 4/7/2026 Approved JAVIER RAMOS JR
Final 4/7/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/7/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 4/7/2026 Approved JAVIER RAMOS JR
Smoke Detectors 4/7/2026 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 4/7/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/8/2026 No Access for Inspection MICHAEL CORTEZ
Final 6/2/2026 OK to Issue CofO RAUL OLAGI