14811-14813 W MCCORMICK ST 91411
Certificate Information: 14811-14813 W MCCORMICK ST 91411
- Application / Permit
- 24010-20000-02508
- Plan Check / Job No.
- B24VN08344
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-Story (88.3' x 59' Irregular Shape) Single Family Dwelling with attached garage, trellis patio cover and Accessory Dwelling Unit per LAMC 12.22 A.33 (c) and (e). NFPA 13D Fire Sprinklers Throughout.
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 6/28/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 7/10/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/16/2024 | APPLICANT |
| Applicant returned to address corrections | 11/14/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 11/20/2024 | VAHAN JIVALAGIAN |
| Issued | 11/20/2024 | APPLICANT |
| CofO in Progress | 6/3/2026 | RAUL OLAGI |
| CofO Issued | 6/9/2026 | RUBEN SALAS |
| Permit Finaled | 6/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 7/29/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2024 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 8/26/2024 | ADALBERTO VERA |
| Construction near power lines | Cleared | 9/5/2024 | RIDWAN HARDY |
| Miscellaneous | Cleared | 9/26/2024 | DORIAN AGUILAR |
| Hydrant and Access approval | Cleared | 10/17/2024 | KURT CORRAL |
| Permit | Cleared | 11/14/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/14/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Urban Culture Design & Development; Lic. No.: 1126457-B | 2219 W OLIVE #306 BURBANK, CA 91506 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/13/2025 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 1/17/2025 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/17/2025 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 1/24/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/28/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 4/22/2025 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 5/8/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 5/13/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/13/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/22/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 5/22/2025 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 5/22/2025 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | JACK KARGODORIAN |
| Insulation | 6/11/2025 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 6/11/2025 | Approved | JACK KARGODORIAN |
| Insulation | 6/23/2025 | Partial Inspection | JACK KARGODORIAN |
| Drywall Nailing | 6/30/2025 | Approved | JACK KARGODORIAN |
| Insulation | 6/30/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 12/22/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/24/2025 | Approved | CRAIG DAVIS |
| HVAC-Final | 12/24/2025 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 4/7/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/7/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/7/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 4/7/2026 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/7/2026 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 4/7/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/8/2026 | No Access for Inspection | MICHAEL CORTEZ |
| Final | 6/2/2026 | OK to Issue CofO | RAUL OLAGI |