8462 N HAZELTINE AVE 91402

Certificate Information: 8462 N HAZELTINE AVE 91402

Application / Permit
24010-20000-02505
Plan Check / Job No.
B24VN08337
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: (N) 1-STORY DETACHED DWELLING UNIT PER SB9, Fully sprinkler NFPA-13D (no split lot)
Permit Issued
Issued on 10/1/2025
Issuing Office
Current Status
Issued on 10/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/14/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 SAM CHANG
Corrections Issued 7/17/2024 SAM CHANG
Quality Review Completed 7/18/2024 EUGENE BARBEAU
Applicant returned to address corrections 8/30/2024 SAM CHANG
Applicant returned to address corrections 6/25/2025 SAM CHANG
Plan Check Approved 10/1/2025 SAM CHANG
Issued 10/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/31/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/31/2024 CARLOS AGUILERA
Sewer availability Cleared 10/31/2024 CARLOS AGUILERA
Construction near power lines Cleared 4/23/2025 GEVORK KARAPETYAN
Low Impact Development (LID) Cleared 4/29/2025 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 5/12/2025 RYAN CASTRO
Senate Bill 9 Cleared 5/12/2025 DAVID URITA
Hydrant and Access approval Cleared 5/29/2025 KURT CORRAL
Miscellaneous Cleared 9/19/2025 MAX LODER

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/8/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/15/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/20/2026 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 1/20/2026 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Approved VINCENT HANLEY
Green Building Rough 1/20/2026 Approved VINCENT HANLEY
HVAC-Rough 1/20/2026 Approved VINCENT HANLEY
PLUMBING-Rough 1/20/2026 Corrections Issued VINCENT HANLEY
Sewer 1/20/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/20/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/10/2026 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/10/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/10/2026 Approved VINCENT HANLEY
PLUMBING-Rough 2/10/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/13/2026 Approved OGANES TARAKHCHYAN
Insulation 2/24/2026 Approved VINCENT HANLEY
Drywall Nailing 2/27/2026 Approved VINCENT HANLEY