13538 W REMINGTON ST 91331

Certificate Information: 13538 W REMINGTON ST 91331

Application / Permit
24010-20000-02502
Plan Check / Job No.
B24VN08334
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 2-story Accessory Dwelling unit per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/19/2024
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 QUAN NGHIEM
Corrections Issued 6/23/2024 QUAN NGHIEM
Quality Review Completed 7/1/2024 PETER KIM
Applicant returned to address corrections 7/26/2024 QUAN NGHIEM
Applicant returned to address corrections 7/29/2024 QUAN NGHIEM
Applicant returned to address corrections 7/31/2024 QUAN NGHIEM
Plan Check Approved 8/7/2024 QUAN NGHIEM
Issued 8/19/2024 APPLICANT
CofO in Progress 4/29/2025 MICHEL ABAJAN
Permit Finaled 7/22/2025 RUBEN SALAS
Permit Finaled 7/22/2025 RUBEN SALAS
CofO Issued 7/22/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/8/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/10/2024 CARLOS RAMIREZ
Sewer availability Cleared 7/10/2024 CARLOS RAMIREZ
Construction near power lines Cleared 7/17/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2024 Approved JENNIFER RABUCHIN
Pre-Inspection 10/4/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 11/5/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/5/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 11/5/2024 Approved MICHEL ABAJAN
HVAC-Rough 11/5/2024 Approved MICHEL ABAJAN
MERV13>=Rough 11/5/2024 Approved MICHEL ABAJAN
METHANE-Rough 11/5/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 11/5/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 11/5/2024 Approved MICHEL ABAJAN
Wood Frame 11/5/2024 Partial Inspection MICHEL ABAJAN
Insulation 11/18/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/18/2024 Approved MICHEL ABAJAN
Drywall Nailing 11/25/2024 Partial Approval LOUIS ESCOTO
Interior/Exterior Lathing 12/4/2024 Approved MICHEL ABAJAN
Drywall Nailing 4/4/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/4/2025 Approved MICHEL ABAJAN
Final 4/4/2025 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 4/4/2025 Approved MICHEL ABAJAN
Green Building Final 4/4/2025 Approved MICHEL ABAJAN
HVAC-Final 4/4/2025 Approved MICHEL ABAJAN
MERV13>=Final 4/4/2025 Approved MICHEL ABAJAN
METHANE-Barrier 4/4/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 4/4/2025 Approved MICHEL ABAJAN
PLUMBING-Final 4/4/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 4/4/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/4/2025 Approved MICHEL ABAJAN
Final 4/25/2025 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 4/25/2025 Approved MICHEL ABAJAN