11307 N AMESTOY AVE 91344

Certificate Information: 11307 N AMESTOY AVE 91344

Application / Permit
24010-20000-02497
Plan Check / Job No.
B24VN08317
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT EXISTING GARAGE WITH ADDITION INTO A 1-STORY (41'-6" x 34'-4" IRREGULAR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) - (d)
Permit Issued
Issued on 11/20/2024
Issuing Office
Current Status
CofO Issued on 5/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 VAHAN JIVALAGIAN
Corrections Issued 7/6/2024 VAHAN JIVALAGIAN
Quality Review Completed 7/10/2024 OMID HEDAYAT
Applicant returned to address corrections 8/9/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 10/21/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/1/2024 VAHAN JIVALAGIAN
Issued 11/20/2024 APPLICANT
CofO in Progress 5/10/2025 STEVEN BACK
CofO Issued 5/12/2025 JOHN JANSON
Permit Finaled 5/12/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/16/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/16/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/31/2024 EDGAR ALCARAZ
Sewer availability Cleared 7/31/2024 EDGAR ALCARAZ
GPI Written Notices Cleared 8/8/2024 VAHAN JIVALAGIAN
Grading Pre-Inspection Cleared 8/8/2024 VAHAN JIVALAGIAN
Construction near power lines Cleared 10/28/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/20/2024 Corrections Issued STEVEN BACK
PLUMBING-Rough 12/24/2024 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 12/30/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/14/2025 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 2/25/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Corrections Issued STEVEN BACK
HVAC-Rough 2/25/2025 Corrections Issued STEVEN BACK
PLUMBING-Rough 2/25/2025 Approved STEVEN BACK
Special/Order Compliance 2/25/2025 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 3/11/2025 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval STEVEN BACK
Green Building Rough 3/11/2025 Partial Approval STEVEN BACK
Insulation 3/11/2025 Partial Approval STEVEN BACK
MERV13>=Rough 3/11/2025 Approved STEVEN BACK
BUILDING-Rough-Frame 3/17/2025 Corrections Issued STEVEN BACK
Drywall Nailing 3/17/2025 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 3/27/2025 Not Ready for Inspection STEVEN BACK
Green Building Rough 3/27/2025 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 4/14/2025 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 4/14/2025 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 4/17/2025 Partial Inspection SEAN WIRCH
Special/Order Compliance 4/17/2025 Corrections Issued SEAN WIRCH
BUILDING-Rough-Frame 5/7/2025 Approved STEVEN BACK
Drywall Nailing 5/7/2025 Approved STEVEN BACK
Final 5/7/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 5/7/2025 Approved STEVEN BACK
Green Building Final 5/7/2025 Approved STEVEN BACK
Green Building Rough 5/7/2025 Approved STEVEN BACK
MERV13>=Final 5/7/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved STEVEN BACK
Service/Power Release 5/7/2025 Approved STEVEN BACK
Smoke Detectors 5/7/2025 Corrections Issued STEVEN BACK
Final 5/9/2025 OK to Issue CofO STEVEN BACK
Smoke Detectors 5/9/2025 Approved STEVEN BACK