10405 N RUFFNER AVE 91344

Certificate Information: 10405 N RUFFNER AVE 91344

Application / Permit
24010-20000-02490
Plan Check / Job No.
B24VN08288
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER WFPP
Permit Issued
Issued on 10/22/2024
Issuing Office
Current Status
Issued on 10/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/11/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 ALFRED RAMIREZ
Corrections Issued 6/28/2024 ALFRED RAMIREZ
Quality Review Completed 7/10/2024 STEVEN KIM
Building Plans Picked Up 7/10/2024 APPLICANT
Applicant returned to address corrections 10/17/2024 ALFRED RAMIREZ
Plan Check Approved 10/22/2024 ALFRED RAMIREZ
Issued 10/22/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/16/2024 CARLOS AGUILERA
Sewer availability Cleared 7/16/2024 CARLOS AGUILERA
Construction within easement Cleared 10/10/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/29/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 5/29/2025 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 6/4/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/4/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/9/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 6/9/2025 Approved CHRISTOPHER ROJAS
Pre-Inspection 6/9/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/16/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Corrections Issued CHRISTOPHER ROJAS
Special/Order Compliance 7/16/2025 Corrections Issued CHRISTOPHER ROJAS
Pre-Inspection 7/21/2025 Partial Approval CHRISTOPHER ROJAS
Wood Frame 7/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/6/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/6/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 8/6/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 8/6/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 8/6/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 8/6/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Approved CHRISTOPHER ROJAS
Gas Test 8/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 8/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/12/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 8/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 8/20/2025 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 8/22/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/22/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 8/22/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 9/4/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/15/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 1/23/2026 Corrections Issued CHRISTOPHER ROJAS
Final 1/23/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/23/2026 Approved CHRISTOPHER ROJAS
Green Building Final 1/23/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 1/23/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 1/23/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 1/23/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/23/2026 Approved CHRISTOPHER ROJAS
Final 2/12/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 2/12/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/2/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 3/2/2026 Not Ready for Inspection JENNIFER RABUCHIN