15248 W MAYALL ST 91345
Certificate Information: 15248 W MAYALL ST 91345
- Application / Permit
- 24010-20000-02475
- Plan Check / Job No.
- B24VN08236
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY S.F.D. PER SB9 TWO UNIT DEVELOPMENT PER ENGINEERING. FIRE SPRINKLER NFPA-13D THRU-OUT
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- Issued on 7/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | ALFRED RAMIREZ |
| Corrections Issued | 6/17/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 6/20/2024 | STEVEN KIM |
| Building Plans Picked Up | 6/20/2024 | APPLICANT |
| Applicant returned to address corrections | 7/16/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 7/16/2024 | ALFRED RAMIREZ |
| Issued | 7/16/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/24/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/24/2024 | CARLOS RAMIREZ |
| Senate Bill 9 | Cleared | 6/28/2024 | DORIAN AGUILAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/25/2024 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/2/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 1/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/27/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 2/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 2/27/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 3/3/2025 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 4/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/1/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/22/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Insulation | 5/2/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/8/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/26/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/26/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 8/26/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/17/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 3/25/2026 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 3/25/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/18/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 5/18/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 5/18/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 5/18/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 5/18/2026 | Approved | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 5/18/2026 | Approved | GAREN HAYRAPETYAN |