173 E 36TH ST 90011
Certificate Information: 173 E 36TH ST 90011
- Application / Permit
- 24010-20000-02469
- Plan Check / Job No.
- B24VN07696
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan:NEW 2-STORY SFD (REAR LOT) -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 11/8/2024
- Issuing Office
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/11/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/21/2024 | TU HUA |
| Applicant returned to address corrections | 10/11/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/29/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 11/7/2024 | CHAD DOI |
| Issued | 11/8/2024 | APPLICANT |
| CofO in Progress | 6/11/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
| CofO Issued | 6/17/2025 | DEROLD HAUFF |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2024 | CHRISTINA BRACO |
| Low Impact Development (LID) | Cleared | 7/16/2024 | SARAH YOUSSEF |
| Permit | Cleared | 8/1/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/13/2024 | CHRISTINA BRACO |
| SB8 RUD | Cleared | 8/20/2024 | ASHLEY MEDINA |
| Roof/Waste drainage to street | Cleared | 8/26/2024 | CHRISTINA BRACO |
| Trees in Parkway | Cleared | 9/10/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 10/1/2024 | PATRICK PEREZ |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 12/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 12/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 2/28/2025 | Approved | ANTHONY RAMOS |
| Verify Rec and Parks Fee Memo | 3/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/12/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 3/12/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 3/12/2025 | Approved | ANTHONY RAMOS |
| Verify Sprinkler Sign Off | 3/12/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 3/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/10/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/10/2025 | Approved | ALEJANDRO DE ARTOLA |