2422 S CASTLE HEIGHTS AVE 90034

Certificate Information: 2422 S CASTLE HEIGHTS AVE 90034

Application / Permit
24010-20000-02447
Plan Check / Job No.
B24VN08065
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 37' 7" x 16' 6" one story ADU per LAMC 12.22 A.33(c)* and (d)*. All work done per engineer.
Permit Issued
Issued on 10/8/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 NAREG ATARIAN
Corrections Issued 7/9/2024 NAREG ATARIAN
Quality Review Completed 7/9/2024 OMID HEDAYAT
Building Plans Picked Up 7/10/2024 APPLICANT
Applicant returned to address corrections 8/22/2024 NAREG ATARIAN
Applicant returned to address corrections 9/11/2024 NAREG ATARIAN
Plan Check Approved 10/7/2024 NAREG ATARIAN
Issued 10/8/2024 APPLICANT
CofO in Progress 3/5/2026 ANDREW NAVE
Permit Finaled 3/6/2026 RICHARD STEINBACH
CofO Issued 3/6/2026 RICHARD STEINBACH
Permit Finaled 3/6/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/18/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 7/18/2024 LIAM ODONOVAN
Sewer availability Cleared 7/18/2024 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 8/10/2024 LIAM ODONOVAN
GPI Written Notices Cleared 10/7/2024 MATTHEW JENKINS
Grading Pre-Inspection Cleared 10/7/2024 MATTHEW JENKINS

Contact Information

Contractor A 1 Construction & Designs Inc; Lic. No.: 1002697-B 2817 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2024 Corrections Issued ASHLEY THOMPSON
METHANE-Subgrade 11/27/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 11/27/2024 Partial Approval ASHLEY THOMPSON
Underground Mechanical 11/27/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Rough 12/5/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 12/5/2024 Corrections Issued ASHLEY THOMPSON
Deputy Methane Barrier 12/11/2024 Conditional Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 12/16/2024 Approved ARAM AVEDISIAN
METHANE-Barrier 12/16/2024 Approved ARAM AVEDISIAN
METHANE-Subgrade 12/16/2024 Approved ARAM AVEDISIAN
Masonry Wall/Backfill 12/17/2024 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/19/2024 Not Ready for Inspection BOBBY KEY
Special/Order Compliance 12/19/2024 Partial Inspection JAYLIN GRAVITTE
Masonry Wall/Backfill 12/20/2024 Partial Approval ARAM AVEDISIAN
Reinforced Masonry Frame 12/20/2024 Conditional Approval ARAM AVEDISIAN
Sewer 12/23/2024 Approved ARAM AVEDISIAN
Deputy Wood Construction 1/2/2025 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Corrections Issued ASHLEY THOMPSON
Wood Frame 1/2/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 3/14/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 3/14/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 3/14/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 3/24/2025 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 3/24/2025 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 3/24/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 4/9/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Partial Approval ASHLEY THOMPSON
HVAC-Rough 4/9/2025 Corrections Issued ASHLEY THOMPSON
Shower Pan 4/9/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 4/22/2025 Approved STEPHANIE SWANSON
HVAC-Rough 4/22/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 4/23/2025 Not Ready for Inspection ASHLEY THOMPSON
Green Building Rough 4/23/2025 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Rough 4/23/2025 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 4/23/2025 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 4/29/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 4/29/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 4/29/2025 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 4/29/2025 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 5/1/2025 No Access for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 5/5/2025 Approved ARAM AVEDISIAN
Insulation 5/15/2025 Corrections Issued BOBBY KEY
Insulation 5/20/2025 Approved DANIEL VERA
Drywall Nailing 6/4/2025 Approved ARAM AVEDISIAN
HVAC-Final 11/14/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 12/1/2025 Corrections Issued EVAN COOPER
HVAC-Final 12/1/2025 Corrections Issued EVAN COOPER
PLUMBING-Final 12/1/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Final 12/17/2025 Not Ready for Inspection ASHLEY THOMPSON
Final 12/17/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 12/17/2025 Approved ASHLEY THOMPSON
Green Building Final 12/17/2025 Approved ASHLEY THOMPSON
HVAC-Final 12/17/2025 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 12/17/2025 Not Ready for Inspection ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Not Required ASHLEY THOMPSON
Service/Power Release 12/17/2025 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 12/17/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
Final 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 1/13/2026 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 1/13/2026 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 1/13/2026 Corrections Issued ASHLEY THOMPSON
Service/Power Release 1/13/2026 Not Ready for Inspection ASHLEY THOMPSON
Final 2/13/2026 Not Ready for Inspection RYAN SALAZAR
Service/Power Release 2/13/2026 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 2/13/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 3/5/2026 Approved ASHLEY THOMPSON
Final 3/5/2026 OK to Issue CofO ASHLEY THOMPSON
HVAC-Final 3/5/2026 Approved ASHLEY THOMPSON
PLUMBING-Final 3/5/2026 Approved ASHLEY THOMPSON
Service/Power Release 3/5/2026 Approved ASHLEY THOMPSON