6846 N CEDROS AVE 91405
Certificate Information: 6846 N CEDROS AVE 91405
- Application / Permit
- 24010-20000-02436
- Plan Check / Job No.
- B24VN08012
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two stories 30' x 20' Single Family Dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 10/10/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | NAREG ATARIAN |
| Corrections Issued | 6/16/2024 | NAREG ATARIAN |
| Quality Review Completed | 6/17/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/17/2024 | APPLICANT |
| Applicant returned to address corrections | 8/30/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 9/24/2024 | NAREG ATARIAN |
| Plan Check Approved | 10/3/2024 | NAREG ATARIAN |
| Issued | 10/10/2024 | APPLICANT |
| CofO in Progress | 10/30/2025 | RYAN SALAZAR |
| Permit Finaled | 10/31/2025 | RUBEN SALAS |
| CofO Issued | 10/31/2025 | RUBEN SALAS |
| Permit Finaled | 10/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 6/21/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 6/25/2024 | TAL SHEMEN |
| Senate Bill 9 | Cleared | 7/2/2024 | DORIAN AGUILAR |
| Hydrant and Access approval | Cleared | 8/24/2024 | PATRICK PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/27/2024 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 11/27/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 12/3/2024 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Partial Approval | RYAN SALAZAR |
| Wood Frame | 12/11/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/17/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/17/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 3/17/2025 | Approved | RYAN SALAZAR |
| Insulation | 3/28/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/28/2025 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 3/28/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/4/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 4/4/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/29/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | RYAN SALAZAR |
| Final | 10/22/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/22/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 10/22/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 10/22/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 10/22/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 10/22/2025 | Approved | RYAN SALAZAR |
| Final | 10/31/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 10/31/2025 | Approved | RYAN SALAZAR |