16047 1/2 W CHATSWORTH ST 91344

Certificate Information: 16047 1/2 W CHATSWORTH ST 91344

Application / Permit
24010-20000-02427
Plan Check / Job No.
B24VN07978
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW 943 SQ.FT. SFD PER SB9 (per SB9 Two-Unit Development Ca Govt Code 65852.21) + Attached carport 174sqft **13D SPRINKLER REQUIRED***
Permit Issued
Issued on 12/2/2024
Issuing Office
Current Status
Issued on 12/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/5/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 KHUONG TRUONG
Corrections Issued 6/28/2024 KHUONG TRUONG
Quality Review Completed 7/31/2024 HERNAN ARREOLA
Plan Check Approved 11/5/2024 KHUONG TRUONG
Issued 12/2/2024 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/1/2024 HUGO GARRIDO GARZA
Address approval Cleared 8/3/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/3/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/6/2024 CARLOS AGUILERA
Sewer availability Cleared 8/6/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/20/2024 LAVEON RIDER
Senate Bill 9 Cleared 9/23/2024 MATHEW QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/25/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/1/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/7/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/20/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 8/20/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 9/24/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 9/24/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/1/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 10/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 10/1/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/16/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/16/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 10/16/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/27/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 10/27/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/27/2025 Partial Approval CHRISTOPHER ROJAS
MERV13>=Rough 10/27/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 10/27/2025 Approved CHRISTOPHER ROJAS
Insulation 11/7/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 11/7/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/25/2025 Corrections Issued CHRISTOPHER ROJAS