11737 N GREENWOOD DR 91326

Certificate Information: 11737 N GREENWOOD DR 91326

Application / Permit
24010-20000-02424
Plan Check / Job No.
B24VN07966
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW DETACHED PATIO COVER
Permit Issued
Issued on 1/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 10/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 SELLA BENYAMIN
Corrections Issued 7/2/2024 SELLA BENYAMIN
Quality Review Completed 7/10/2024 STEVEN KIM
Building Plans Picked Up 7/11/2024 APPLICANT
Applicant returned to address corrections 9/24/2024 SELLA BENYAMIN
Plan Check Approved 1/21/2025 SELLA BENYAMIN
Issued 1/21/2025 APPLICANT
CofO in Progress 10/28/2025 STEVEN BACK
Permit Finaled 10/30/2025 JOHN JANSON
CofO Issued 10/30/2025 JOHN JANSON
Permit Finaled 10/30/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/2/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/5/2024 LEE GUILBEAUX
"T" removal Cleared 8/7/2024 DORIAN AGUILAR
CPC Cleared 8/7/2024 DORIAN AGUILAR
Miscellaneous Cleared 8/7/2024 DORIAN AGUILAR
Miscellaneous Cleared 8/7/2024 DORIAN AGUILAR
Miscellaneous Cleared 8/7/2024 DORIAN AGUILAR
Specific Plan Cleared 8/7/2024 DORIAN AGUILAR
Tract Map conditions Cleared 8/7/2024 DORIAN AGUILAR
ZA Case Cleared 8/7/2024 DORIAN AGUILAR
ZA Case Cleared 8/7/2024 DORIAN AGUILAR
Private street Cleared 8/8/2024 DORIAN AGUILAR

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/27/2025 Approved STEVEN BACK
Footing/Foundation/Slab 3/27/2025 Approved STEVEN BACK
Masonry Wall/Backfill 4/15/2025 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Approved STEVEN BACK
Light Gage Steel Frame 7/22/2025 Approved STEVEN BACK
BUILDING-Rough-Frame 8/26/2025 Approved STEVEN BACK
Final 8/26/2025 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved STEVEN BACK
Smoke Detectors 8/26/2025 Approved STEVEN BACK
Final 9/9/2025 Not Ready for Inspection JEFFREY PARD
Final 10/9/2025 Not Ready for Inspection STEVEN BACK
Final 10/22/2025 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 10/28/2025 Approved STEVEN BACK
Final 10/28/2025 OK to Issue CofO STEVEN BACK