15359 W LARKSPUR ST 91342

Certificate Information: 15359 W LARKSPUR ST 91342

Application / Permit
24010-20000-02417
Plan Check / Job No.
B24VN07939
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d) WITH ATTACHED PATIO COVERS PER ENGINEERING
Permit Issued
Issued on 7/9/2024
Issuing Office
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2024 APPLICANT
Assigned to Plan Check Engineer 6/12/2024 ALFRED RAMIREZ
Corrections Issued 6/13/2024 ALFRED RAMIREZ
Applicant returned to address corrections 7/2/2024 SERGIO MUNIZ
Plan Check Approved 7/8/2024 SERGIO MUNIZ
Issued 7/9/2024 APPLICANT
CofO in Progress 6/23/2025 KEVIN BERBERYAN
Permit Finaled 7/1/2025 RUBEN SALAS
Permit Finaled 7/1/2025 RUBEN SALAS
CofO Issued 7/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/21/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/21/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/24/2024 TAL SHEMEN
Sewer availability Cleared 6/24/2024 TAL SHEMEN

Contact Information

Contractor Warren Development Llc; Lic. No.: 1098736-B       ,
Engineer Medina,, Armando; Lic. No.: C83911 2000 W LINCOLN AVE      MONTEBELLO, CA 90640

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/16/2024 Partial Inspection KEVIN BERBERYAN
PLUMBING-Rough 8/19/2024 Partial Approval MISAEL ESPARZA
Underground Mechanical 8/21/2024 Partial Approval KRISTEN CAUSEY
Footing/Foundation/Slab 8/22/2024 Approved JENNIFER RABUCHIN
Deputy Reinf. Concrete 8/26/2024 Conditional Approval ROBERT GOLD
Underground Mechanical 8/26/2024 Corrections Issued JACK KARGODORIAN
Underground Mechanical 9/13/2024 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 9/18/2024 Conditional Approval DAVID MATSON
HVAC-Rough 9/20/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/24/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/25/2024 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 9/25/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 9/26/2024 Approved KEVIN BERBERYAN
Shower Pan 9/30/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/1/2024 Approved KEVIN BERBERYAN
HVAC-Final 10/4/2024 Approved KEVIN BERBERYAN
Insulation 10/4/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/4/2024 Approved KEVIN BERBERYAN
Drywall Nailing 10/10/2024 Approved KEVIN BERBERYAN
Green Building Rough 10/10/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/23/2024 Conditional Approval KEVIN BERBERYAN
Final 12/23/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 12/23/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 12/23/2024 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 12/23/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 12/23/2024 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Final 12/26/2024 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 4/17/2025 Approved KEVIN BERBERYAN
Final 4/17/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 4/17/2025 Approved KEVIN BERBERYAN
Service/Power Release 4/17/2025 Approved KEVIN BERBERYAN