13231 W HESBY ST 91423

Certificate Information: 13231 W HESBY ST 91423

Application / Permit
24010-20000-02411
Plan Check / Job No.
B24VN07895
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New two stories 23' 9 1/2" x 21' 3" Single family dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D sprinklers are required. All work done per engineer.
Permit Issued
Issued on 11/8/2024
Issuing Office
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 NAREG ATARIAN
Corrections Issued 6/12/2024 NAREG ATARIAN
Quality Review Completed 6/12/2024 OMID HEDAYAT
Building Plans Picked Up 6/13/2024 APPLICANT
Applicant returned to address corrections 8/28/2024 NAREG ATARIAN
Applicant returned to address corrections 9/9/2024 NAREG ATARIAN
Applicant returned to address corrections 9/13/2024 NAREG ATARIAN
Plan Check Approved 11/8/2024 NAREG ATARIAN
Issued 11/8/2024 APPLICANT
CofO in Progress 10/17/2025 OGANES TARAKHCHYAN
Permit Finaled 10/29/2025 RUBEN SALAS
CofO Issued 10/29/2025 RUBEN SALAS
Permit Finaled 10/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/12/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/12/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/13/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/13/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 7/19/2024 RIDWAN HARDY
Construction within easement Cleared 7/19/2024 RIDWAN HARDY
Senate Bill 9 Cleared 8/20/2024 BRENNEN OBETO
Hydrant and Access approval Cleared 10/31/2024 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/19/2024 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/22/2024 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/27/2024 Approved OGANES TARAKHCHYAN
Deputy Steel/Welding 12/4/2024 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/28/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/28/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 3/28/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 3/28/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/28/2025 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 4/2/2025 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 4/3/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/11/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 4/11/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/14/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/14/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 4/14/2025 Corrections Issued GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 4/14/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/16/2025 Approved GAREN HAYRAPETYAN
Wood Frame 4/16/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved OGANES TARAKHCHYAN
Insulation 4/21/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/21/2025 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 4/25/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 4/25/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/29/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/1/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/13/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 8/12/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 8/12/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 8/12/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 8/20/2025 Approved OGANES TARAKHCHYAN
HVAC-Final 8/20/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Final 8/20/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/28/2025 Approved OGANES TARAKHCHYAN
Final 8/28/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 8/28/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 8/28/2025 Approved OGANES TARAKHCHYAN
Smoke Detectors 8/28/2025 Approved OGANES TARAKHCHYAN
Final 10/8/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 10/16/2025 OK to Issue CofO OGANES TARAKHCHYAN