7777 N FULTON AVE 91605

Certificate Information: 7777 N FULTON AVE 91605

Application / Permit
24010-20000-02381
Plan Check / Job No.
B24VN07822
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: (N) 38'6" X 30' ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 7/16/2024
Issuing Office
Current Status
Issued on 7/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/4/2024 APPLICANT
Assigned to Plan Check Engineer 6/7/2024 OMAR GARNICA
Corrections Issued 6/7/2024 OMAR GARNICA
Applicant returned to address corrections 7/12/2024 NGHI SU
Plan Check Approved 7/15/2024 LUKE GONZALES
Issued 7/16/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 7/3/2024 WALTER RAMIREZ
Address approval Cleared 7/9/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 7/9/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/10/2024 CARLOS RAMIREZ
Sewer availability Cleared 7/10/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/9/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 9/4/2024 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 9/16/2024 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 9/17/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 9/17/2024 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 12/6/2024 Approved VINCENT HANLEY
Sewer 12/6/2024 Approved VINCENT HANLEY
Underground Mechanical 12/6/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/30/2024 Approved VINCENT HANLEY
HVAC-Rough 12/30/2024 Approved VINCENT HANLEY
Underground Mechanical 12/30/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/7/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 2/7/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/7/2025 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 2/7/2025 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 2/7/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 2/25/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 2/25/2025 Approved JACK KARGODORIAN
Green Building Rough 2/25/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 2/25/2025 Approved JACK KARGODORIAN
Insulation 4/2/2025 Approved MICHEL ABAJAN
Drywall Nailing 5/1/2025 Approved JACK KARGODORIAN
Underground Mechanical 5/1/2025 Approved JACK KARGODORIAN