1013 3/4 E 28TH ST 90011
Certificate Information: 1013 3/4 E 28TH ST 90011
- Application / Permit
- 24010-20000-02374
- Plan Check / Job No.
- B24VN07794
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY (15'-0"x24'-0"), 720 SQFT ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) AND LAMC 12.22 A.33 (c)-(d), (g), ALL ELECTRIC BUILDING
- Permit Issued
- Issued on 10/29/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | PETER MOSESIAN |
| Corrections Issued | 6/23/2024 | PETER MOSESIAN |
| Quality Review Completed | 6/27/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/28/2024 | APPLICANT |
| Plan Check Approved | 10/28/2024 | PETER MOSESIAN |
| Issued | 10/29/2024 | APPLICANT |
| CofO in Progress | 3/24/2026 | ALEJANDRO DE ARTOLA |
| No Progress | 3/24/2026 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 3/24/2026 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 3/24/2026 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 5/7/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 5/13/2026 | DEROLD HAUFF |
| CofO Issued | 5/13/2026 | DEROLD HAUFF |
| Permit Finaled | 5/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/12/2024 | ADRIAN SANCHEZ |
| Historic monument | Cleared | 9/26/2024 | LAMBERT GIESSINGER |
| ZI | Cleared | 9/26/2024 | LAMBERT GIESSINGER |
| Construction near power lines | Cleared | 10/1/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2024 | CELINA MORENO |
| Sewer availability | Cleared | 10/28/2024 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/4/2024 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 11/6/2024 | Corrections Issued | AMIR NAZARIAN |
| Pre-Inspection | 11/6/2024 | Corrections Issued | AMIR NAZARIAN |
| Special/Order Compliance | 11/6/2024 | Partial Inspection | ALEX COLIN |
| Footing/Foundation/Slab | 11/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/24/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 12/27/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 12/27/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/31/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/31/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/3/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/18/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/5/2025 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 5/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/10/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 6/10/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 10/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/28/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/28/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/24/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/24/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/11/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/23/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/23/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/23/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/23/2026 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/23/2026 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/23/2026 | Approved | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 3/24/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/6/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |