4718 N LEMONA AVE 91403

Certificate Information: 4718 N LEMONA AVE 91403

Application / Permit
24010-20000-02366
Plan Check / Job No.
B24VN07778
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE IRREG. 38'X70'-6" TWO STORY SFD WITH ATTACH TWO CAR GARAGE_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 9/9/2024
Issuing Office
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 DAWN MC NULTY
Corrections Issued 6/13/2024 DAWN MC NULTY
Quality Review Completed 6/17/2024 OMID HEDAYAT
Building Plans Picked Up 7/3/2024 APPLICANT
Applicant returned to address corrections 7/15/2024 DAWN MC NULTY
Applicant returned to address corrections 8/22/2024 DAWN MC NULTY
Plan Check Approved 9/5/2024 DAWN MC NULTY
Plan Check Approved 9/5/2024 DAWN MC NULTY
No Progress 9/5/2024 DAWN MC NULTY
Plan Check Approved 9/9/2024 DAWN MC NULTY
Issued 9/9/2024 APPLICANT
CofO in Progress 6/25/2025 JACK KARGODORIAN
Permit Finaled 7/29/2025 RUBEN SALAS
CofO Issued 7/29/2025 RUBEN SALAS
Permit Finaled 7/29/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/18/2024 SARAH YOUSSEF
Address approval Cleared 6/21/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/21/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/3/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/5/2024 BIAINA HARITUNIAN
Trees in Parkway Cleared 7/8/2024 ADALBERTO VERA
Permit Cleared 7/16/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 7/26/2024 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/1/2024 Partial Approval JACK KARGODORIAN
Underground Mechanical 10/1/2024 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 10/4/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 10/4/2024 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/10/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 10/24/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Approved JACK KARGODORIAN
HVAC-Rough 12/10/2024 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 12/10/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval JACK KARGODORIAN
Green Building Rough 12/20/2024 Approved JACK KARGODORIAN
HVAC-Rough 12/20/2024 Approved JACK KARGODORIAN
MERV13>=Rough 12/20/2024 Approved JACK KARGODORIAN
Shower Pan 12/20/2024 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 12/20/2024 Approved JACK KARGODORIAN
ELECTRICAL-Rough 1/6/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 1/8/2025 Partial Inspection MISAEL ESPARZA
Shower Pan 1/8/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 1/9/2025 Approved JACK KARGODORIAN
HVAC-Rough 1/15/2025 Approved OGANES TARAKHCHYAN
Insulation 1/15/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/15/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/17/2025 Approved JACK KARGODORIAN
Drywall Nailing 1/24/2025 Partial Approval LOUIS ESCOTO
Drywall Nailing 6/4/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 6/4/2025 Not Ready for Inspection JACK KARGODORIAN
Final 6/4/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 6/4/2025 Approved JACK KARGODORIAN
HVAC-Final 6/4/2025 Approved JACK KARGODORIAN
MERV13>=Final 6/4/2025 Approved JACK KARGODORIAN
PLUMBING-Final 6/4/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Not Ready JACK KARGODORIAN
Service/Power Release 6/4/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 6/4/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 6/9/2025 Approved JACK KARGODORIAN
Final 6/9/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 6/9/2025 Approved JACK KARGODORIAN
PLUMBING-Final 6/9/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Not Required JACK KARGODORIAN
Service/Power Release 6/9/2025 Not Ready for Inspection JACK KARGODORIAN
Final 6/24/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 6/24/2025 Approved JACK KARGODORIAN