11106 N NORRIS AVE 91331
Certificate Information: 11106 N NORRIS AVE 91331
- Application / Permit
- 24010-20000-02360
- Plan Check / Job No.
- B24VN07769
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY (26'-0"x49'-0"), 1200 SQFT ADU PER CA Govt. Code AND 65852.2(e)(1)(D) LAMC 12.22 A.33 (c)-(d), (g), W/NFPA 13D SPRINKLERS THROUGHOUT. ALL ELECTRIC BUILDING. WORK DONE USING WFPP
- Permit Issued
- Issued on 11/1/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | PETER MOSESIAN |
| Corrections Issued | 6/22/2024 | PETER MOSESIAN |
| Quality Review Completed | 6/27/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/28/2024 | APPLICANT |
| Plan Check Approved | 11/1/2024 | PETER MOSESIAN |
| Issued | 11/1/2024 | APPLICANT |
| CofO in Progress | 6/27/2025 | MICHEL ABAJAN |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 7/9/2024 | BRENNEN OBETO |
| ZI | Cleared | 7/9/2024 | BRENNEN OBETO |
| Address approval | Cleared | 7/15/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/15/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 9/26/2024 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 10/30/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 10/30/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 11/27/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 11/27/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 11/27/2024 | Partial Approval | MICHEL ABAJAN |
| METHANE-Subgrade | 12/4/2024 | Approved | MICHEL ABAJAN |
| Deputy Methane Barrier | 12/12/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 12/16/2024 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/16/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 12/16/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | MICHEL ABAJAN |
| Sewer | 1/6/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/14/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 1/14/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/14/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/3/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/3/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/3/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 2/3/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/3/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/14/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/21/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/12/2025 | Approved | MICHEL ABAJAN |
| Final | 6/12/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/12/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/12/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/12/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/12/2025 | Approved | MICHEL ABAJAN |
| Final | 6/24/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 6/24/2025 | Approved | MICHEL ABAJAN |