9320 W MONTE MAR DR 90035
Certificate Information: 9320 W MONTE MAR DR 90035
- Application / Permit
- 24010-20000-02341
- Plan Check / Job No.
- B24VN07706
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-Story (68'-7" x 39'-9" Irregular Shape) Single Family Dwelling with habitable basement, garage and trellis patio cover. NFPA 13D Fire Sprinklers Throughout.
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Valley
- Current Status
- Issued on 10/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 6/9/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 6/12/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/17/2024 | APPLICANT |
| Applicant returned to address corrections | 7/25/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 8/28/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 9/25/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 10/9/2024 | VAHAN JIVALAGIAN |
| Issued | 10/9/2024 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 6/10/2024 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 6/10/2024 | VAHAN JIVALAGIAN |
| Address approval | Cleared | 7/23/2024 | DARIN LAM |
| Permit | Cleared | 7/23/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/24/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 7/25/2024 | DARIN LAM |
| Hydrant and Access approval | Cleared | 8/10/2024 | JOHN CONNEALLY |
| Excavation more than 5-ft deep | Cleared | 8/28/2024 | CALOSHA APPROVED |
| Trees in Parkway | Cleared | 10/4/2024 | ADALBERTO VERA |
Contact Information
| Architect | Gilliam,, Jonathan; Lic. No.: C33995 | 15017 ARCHWOOD STREET VAN NUYS, CA 91405 |
| Contractor | Diamond Financial Management Inc; Lic. No.: 1093438-B | 325 N MAPLE DR #17777 BEVERLY HILLS, CA 90209 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/6/2024 | Partial Inspection | BOBBY KEY |
| Pre-Inspection | 1/10/2025 | Partial Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 1/29/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/31/2025 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/26/2025 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 2/26/2025 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 2/26/2025 | Not Ready for Inspection | EVAN COOPER |
| Deputy Reinf. Concrete | 2/28/2025 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 3/28/2025 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Partial Approval | ARAM AVEDISIAN |
| Deputy Methane Barrier | 4/17/2025 | Conditional Approval | EVAN COOPER |
| METHANE-Barrier | 4/18/2025 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 4/18/2025 | Partial Approval | EVAN COOPER |
| Deputy Shotcrete | 4/23/2025 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Methane Barrier | 4/30/2025 | Conditional Approval | EVAN COOPER |
| Deputy Methane Barrier | 5/15/2025 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 5/21/2025 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 5/21/2025 | Approved | EVAN COOPER |
| METHANE-Subgrade | 5/21/2025 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 5/22/2025 | Conditional Approval | ASHLEY THOMPSON |
| METHANE-Final | 6/5/2025 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 6/5/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 6/16/2025 | Corrections Issued | ARAM AVEDISIAN |
| METHANE-Barrier | 6/16/2025 | Approved | ARAM AVEDISIAN |
| Structural Steel Frame | 6/20/2025 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/2/2025 | Approved | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 7/9/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 10/29/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 11/3/2025 | Approved | EVAN COOPER |
| Special/Order Compliance | 11/3/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 11/13/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 11/18/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/4/2025 | Conditional Approval | EVAN COOPER |
| Interior/Exterior Lathing | 12/15/2025 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/6/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 1/6/2026 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 1/6/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 1/6/2026 | Approved | ASHLEY THOMPSON |
| Shower Pan | 1/6/2026 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 1/6/2026 | Approved | ASHLEY THOMPSON |
| Insulation | 1/20/2026 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 2/3/2026 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 2/25/2026 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/25/2026 | Approved | WILBER ROSALES |