233-233 1/2 E 93RD ST 90003

Certificate Information: 233-233 1/2 E 93RD ST 90003

Application / Permit
24010-20000-02334
Plan Check / Job No.
B24VN07691
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 11/12/2024
Issuing Office
Current Status
CofO Issued on 4/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 MAHNAZ NOURHASHEMI
Corrections Issued 6/10/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 6/14/2024 TU HUA
Plan Check Approved 10/31/2024 MAHNAZ NOURHASHEMI
Issued 11/12/2024 APPLICANT
CofO in Progress 4/17/2025 JOHN QUINTANILLA
Permit Finaled 4/19/2025 DEROLD HAUFF
CofO Issued 4/19/2025 DEROLD HAUFF
Permit Finaled 4/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/16/2024 SARAH YOUSSEF
Address approval Cleared 8/1/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 8/1/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 8/7/2024 AMBER CAMPBELL
Sewer availability Cleared 8/14/2024 TREVOR QUAN
Trees in Parkway Cleared 9/10/2024 ADALBERTO VERA
Frnt yard landscape/Water mgmt Cleared 9/24/2024 FIPE LEILUA
Permit Cleared 9/27/2024 TREVOR QUAN
Hydrant and Access approval Cleared 10/7/2024 PATRICK PEREZ
SB8 RUD Cleared 10/23/2024 LOUIE MILLER

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/9/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 12/9/2024 Approved MICHAEL LEWIS
Underground Mechanical 12/17/2024 Approved JOHN QUINTANILLA
Wood Frame 12/17/2024 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Partial Approval NICHOLAS LOPEZ
Insulation 12/18/2024 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 2/6/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 2/7/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 2/7/2025 Corrections Issued JOHN QUINTANILLA
Green Building Rough 2/7/2025 Not Ready for Inspection JOHN QUINTANILLA
Verify Sprinkler Sign Off 2/7/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 2/12/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Rough 2/12/2025 Approved JOHN QUINTANILLA
Green Building Rough 2/12/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 2/12/2025 Approved JOHN QUINTANILLA
Insulation 2/13/2025 Approved JOHN QUINTANILLA
Drywall Nailing 2/26/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 2/26/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 2/27/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 3/27/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 4/3/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 4/3/2025 Approved JOHN QUINTANILLA
Green Building Final 4/3/2025 Approved JOHN QUINTANILLA
Green Building Rough 4/3/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Required JOHN QUINTANILLA
HVAC-Final 4/7/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 4/7/2025 Approved JOHN QUINTANILLA
Service/Power Release 4/7/2025 Approved JOHN QUINTANILLA
Final 4/9/2025 OK to Issue CofO JOHN QUINTANILLA
PLUMBING-Final 4/9/2025 Approved JOHN QUINTANILLA
Smoke Detectors 4/9/2025 Approved JOHN QUINTANILLA