7425 N CALDUS AVE 91406

Certificate Information: 7425 N CALDUS AVE 91406

Application / Permit
24010-20000-02306
Plan Check / Job No.
B24VN07596
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREG SHAPED DETACHED FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). SEE COMMENTS.
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
Issued on 1/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/17/2024 APPLICANT
Assigned to Plan Check Engineer 7/24/2024 JEROME MAGAT PALMA
Corrections Issued 7/24/2024 JEROME MAGAT PALMA
Building Plans Picked Up 8/1/2024 APPLICANT
Plan Check Approved 1/17/2025 HAYATO TSUCHIYA
Plan Check Approved 1/17/2025 HAYATO TSUCHIYA
Issued 1/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/30/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 9/30/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 9/30/2024 CARLOS RAMIREZ
Sewer availability Cleared 10/9/2024 CARLOS RAMIREZ
Construction within easement Cleared 1/16/2025 GEVORK KARAPETYAN

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD 230      TARZANA, CA 91356
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/26/2025 Corrections Issued GAREN HAYRAPETYAN
Sewer 2/26/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 2/26/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 3/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/6/2025 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 3/20/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 4/8/2025 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 4/24/2025 Corrections Issued SALVADOR MARTINEZ
Special/Order Compliance 4/24/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 4/28/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 6/24/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 6/24/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 6/30/2025 Conditional Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 6/30/2025 Corrections Issued GAREN HAYRAPETYAN
Wood Frame 6/30/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 7/3/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 7/3/2025 Approved SALVADOR MARTINEZ
Green Building Rough 7/3/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 7/3/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 7/3/2025 Partial Approval SALVADOR MARTINEZ
Verify Sprinkler Sign Off 7/3/2025 Approved SALVADOR MARTINEZ
Insulation 7/10/2025 Corrections Issued LOUIS ESCOTO
Shower Pan 7/10/2025 Approved LOUIS ESCOTO
Drywall Nailing 7/15/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/29/2025 Approved LOUIS ESCOTO
Pre-Inspection 11/5/2025 Partial Inspection GAREN HAYRAPETYAN