824 N CURSON AVE 90046

Certificate Information: 824 N CURSON AVE 90046

Application / Permit
24010-20000-02281
Plan Check / Job No.
B24VN07490
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 84' X 38' TWO STORIES SFD WITH ATTACHED 2 CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/4/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 RARES BODEA
Corrections Issued 6/4/2024 RARES BODEA
Quality Review Completed 6/12/2024 STEVEN KIM
Building Plans Picked Up 6/14/2024 APPLICANT
Applicant returned to address corrections 8/29/2024 RARES BODEA
Plan Check Approved 9/3/2024 RARES BODEA
Issued 9/4/2024 APPLICANT
CofO in Progress 4/27/2026 JOSH MEISTER
Permit Finaled 5/1/2026 DEROLD HAUFF
CofO Issued 5/1/2026 DEROLD HAUFF
Permit Finaled 5/1/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/20/2024 SARAH YOUSSEF
Address approval Cleared 6/25/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 6/25/2024 DAVID LOPEZ
Permit Cleared 7/2/2024 DAVID LOPEZ
Sewer availability Cleared 7/2/2024 DAVID LOPEZ
Trees in Parkway Cleared 7/11/2024 MIGUEL ORNELAS
Eng Process Fee Ord 176,300 Cleared 7/17/2024 DAVID LOPEZ
ZI Cleared 7/19/2024 ROSALINDA MEZA
Hydrant and Access approval Cleared 8/22/2024 PATRICK PEREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/30/2024 Partial Approval JOSE MACIAS
Underground Mechanical 10/30/2024 Approved JOSE MACIAS
Deputy Reinf. Concrete 11/7/2024 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 11/7/2024 Approved JOSE MACIAS
Deputy Reinf. Concrete 11/8/2024 Conditional Approval JOAQUIN GREENOUGH
Deputy Steel/Welding 11/18/2024 Conditional Approval JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 No Access for Inspection JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 1/31/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 2/13/2025 Not Ready for Inspection JOSE MACIAS
HVAC-Rough 2/13/2025 Approved JOSE MACIAS
PLUMBING-Rough 2/13/2025 Approved JOSE MACIAS
ELECTRICAL-Rough 2/20/2025 Approved JOSE MACIAS
HVAC-Rough 2/20/2025 Approved JOSE MACIAS
PLUMBING-Rough 2/20/2025 Approved JOSE MACIAS
Shower Pan 2/20/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 2/26/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 3/3/2025 Not Ready for Inspection JOSE MACIAS
Green Building Rough 3/3/2025 Not Ready for Inspection JOSE MACIAS
Verify Sprinkler Sign Off 3/3/2025 Not Ready for Inspection JOSE MACIAS
Wood Frame 3/3/2025 Not Ready for Inspection JOSE MACIAS
BUILDING-Rough-Frame 3/5/2025 Corrections Issued JOSE MACIAS
Green Building Rough 3/5/2025 Approved JOSE MACIAS
Verify Sprinkler Sign Off 3/5/2025 Approved JOSE MACIAS
Wood Frame 3/5/2025 Not Ready for Inspection JOSE MACIAS
Insulation 3/11/2025 Partial Approval JOSE MACIAS
Drywall Nailing 3/18/2025 Not Ready for Inspection JOSE MACIAS
Interior/Exterior Lathing 4/22/2025 Approved JOSE MACIAS
Pre-Inspection 7/28/2025 Partial Approval JOSE MACIAS
Special/Order Compliance 8/1/2025 Approved JOSE MACIAS
Special/Order Compliance 8/11/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 8/14/2025 Not Ready for Inspection WAYNE REGESTER
BUILDING-Rough-Frame 12/18/2025 Approved JOSH MEISTER
Drywall Nailing 12/18/2025 Approved JOSH MEISTER
Final 12/18/2025 Corrections Issued JOSH MEISTER
Green Building Final 12/18/2025 Not Ready for Inspection JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Not Required JOSH MEISTER
Service/Power Release 12/18/2025 Not Ready for Inspection JOSH MEISTER
Smoke Detectors 12/18/2025 Approved JOSH MEISTER
Service/Power Release 2/20/2026 Not Ready for Inspection JOSH MEISTER
Service/Power Release 3/9/2026 Not Ready for Inspection JOSH MEISTER
Final 4/23/2026 OK to Issue CofO JOSH MEISTER
Green Building Final 4/23/2026 Approved JOSH MEISTER
Service/Power Release 4/23/2026 Approved JOSH MEISTER