824 N CURSON AVE 90046
Certificate Information: 824 N CURSON AVE 90046
- Application / Permit
- 24010-20000-02281
- Plan Check / Job No.
- B24VN07490
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 84' X 38' TWO STORIES SFD WITH ATTACHED 2 CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | RARES BODEA |
| Corrections Issued | 6/4/2024 | RARES BODEA |
| Quality Review Completed | 6/12/2024 | STEVEN KIM |
| Building Plans Picked Up | 6/14/2024 | APPLICANT |
| Applicant returned to address corrections | 8/29/2024 | RARES BODEA |
| Plan Check Approved | 9/3/2024 | RARES BODEA |
| Issued | 9/4/2024 | APPLICANT |
| CofO in Progress | 4/27/2026 | JOSH MEISTER |
| Permit Finaled | 5/1/2026 | DEROLD HAUFF |
| CofO Issued | 5/1/2026 | DEROLD HAUFF |
| Permit Finaled | 5/1/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 6/20/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 6/25/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/25/2024 | DAVID LOPEZ |
| Permit | Cleared | 7/2/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/2/2024 | DAVID LOPEZ |
| Trees in Parkway | Cleared | 7/11/2024 | MIGUEL ORNELAS |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2024 | DAVID LOPEZ |
| ZI | Cleared | 7/19/2024 | ROSALINDA MEZA |
| Hydrant and Access approval | Cleared | 8/22/2024 | PATRICK PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2024 | Partial Approval | JOSE MACIAS |
| Underground Mechanical | 10/30/2024 | Approved | JOSE MACIAS |
| Deputy Reinf. Concrete | 11/7/2024 | Conditional Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 11/7/2024 | Approved | JOSE MACIAS |
| Deputy Reinf. Concrete | 11/8/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 11/18/2024 | Conditional Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | No Access for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 1/31/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 2/13/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 2/13/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 2/13/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 2/20/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 2/20/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 2/20/2025 | Approved | JOSE MACIAS |
| Shower Pan | 2/20/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 2/26/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/3/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 3/3/2025 | Not Ready for Inspection | JOSE MACIAS |
| Verify Sprinkler Sign Off | 3/3/2025 | Not Ready for Inspection | JOSE MACIAS |
| Wood Frame | 3/3/2025 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/5/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 3/5/2025 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 3/5/2025 | Approved | JOSE MACIAS |
| Wood Frame | 3/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Insulation | 3/11/2025 | Partial Approval | JOSE MACIAS |
| Drywall Nailing | 3/18/2025 | Not Ready for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 4/22/2025 | Approved | JOSE MACIAS |
| Pre-Inspection | 7/28/2025 | Partial Approval | JOSE MACIAS |
| Special/Order Compliance | 8/1/2025 | Approved | JOSE MACIAS |
| Special/Order Compliance | 8/11/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 8/14/2025 | Not Ready for Inspection | WAYNE REGESTER |
| BUILDING-Rough-Frame | 12/18/2025 | Approved | JOSH MEISTER |
| Drywall Nailing | 12/18/2025 | Approved | JOSH MEISTER |
| Final | 12/18/2025 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 12/18/2025 | Not Ready for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Not Required | JOSH MEISTER |
| Service/Power Release | 12/18/2025 | Not Ready for Inspection | JOSH MEISTER |
| Smoke Detectors | 12/18/2025 | Approved | JOSH MEISTER |
| Service/Power Release | 2/20/2026 | Not Ready for Inspection | JOSH MEISTER |
| Service/Power Release | 3/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| Final | 4/23/2026 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 4/23/2026 | Approved | JOSH MEISTER |
| Service/Power Release | 4/23/2026 | Approved | JOSH MEISTER |