17411 W OSBORNE ST 91325

Certificate Information: 17411 W OSBORNE ST 91325

Application / Permit
24010-20000-02280
Plan Check / Job No.
B24VN07488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW GARAGE/STORAGE AND HALF BATH
Permit Issued
Issued on 10/8/2024
Issuing Office
Current Status
Issued on 10/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 SELLA BENYAMIN
Corrections Issued 6/11/2024 SELLA BENYAMIN
Quality Review Completed 6/14/2024 STEVEN KIM
Building Plans Picked Up 6/14/2024 APPLICANT
Plan Check Approved 10/8/2024 SELLA BENYAMIN
Issued 10/8/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/18/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 7/3/2024 WALTER RAMIREZ
Hydrant and Access approval Cleared 8/28/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 9/26/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 9/26/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DR      DUARTE, CA 91010

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/11/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 12/11/2024 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 12/30/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/30/2024 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 12/30/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 6/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 6/26/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 8/8/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 8/8/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 8/8/2025 Partial Approval NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 8/22/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/10/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 10/10/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 10/10/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 10/10/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 10/10/2025 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/10/2025 Approved NICHOLAS TROWBRIDGE
Insulation 11/3/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 11/14/2025 Approved CHRISTOPHER MORFIN
Interior/Exterior Lathing 1/20/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 1/20/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/11/2026 Approved CHRISTOPHER ROJAS
Shower Pan 2/11/2026 Corrections Issued CHRISTOPHER ROJAS