5656 N WINNETKA AVE 91367
Certificate Information: 5656 N WINNETKA AVE 91367
- Application / Permit
- 24010-20000-02279
- Plan Check / Job No.
- B24VN06391
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 38'-2" X 46'-8" IRREGULAR SHAPED ACCESSORY DWELLING UNIT W/ 2-CAR GARAGE AND TRELLIS PATIO. NFPA 13R FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 10/17/2024
- Issuing Office
- Current Status
- CofO Issued on 8/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | RAPHAEL ROSAS |
| Corrections Issued | 5/31/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 6/13/2024 | STEVEN KIM |
| Applicant returned to address corrections | 9/6/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 9/16/2024 | RAPHAEL ROSAS |
| Issued | 10/17/2024 | APPLICANT |
| CofO in Progress | 7/22/2025 | JON MCHUGH |
| Permit Finaled | 8/10/2025 | RUBEN SALAS |
| CofO Issued | 8/10/2025 | RUBEN SALAS |
| Permit Finaled | 8/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | CARLOS AGUILERA |
| Watercourse | Cleared | 6/1/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/3/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 7/12/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/19/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 8/5/2024 | KURT CORRAL |
| GPI Written Notices | Cleared | 9/12/2024 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 9/12/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2024 | Partial Approval | JON MCHUGH |
| Deputy Reinf. Concrete | 11/26/2024 | Approved | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/3/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 1/3/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 1/3/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Partial Approval | JON MCHUGH |
| Shower Pan | 1/7/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/9/2025 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 1/23/2025 | Partial Approval | JON MCHUGH |
| Special/Order Compliance | 1/23/2025 | Partial Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | JON MCHUGH |
| Green Building Rough | 1/28/2025 | Approved | JON MCHUGH |
| Insulation | 1/28/2025 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 1/28/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 1/28/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 1/31/2025 | Approved | JON MCHUGH |
| Insulation | 1/31/2025 | Approved | JON MCHUGH |
| Sewer | 4/1/2025 | Approved | JON MCHUGH |
| Underground Mechanical | 4/4/2025 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Final | 5/23/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 5/23/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 6/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 6/24/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 6/24/2025 | Approved | JON MCHUGH |
| HVAC-Final | 6/24/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 6/24/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Not Required | JON MCHUGH |
| Smoke Detectors | 6/24/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 6/27/2025 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 6/27/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 6/27/2025 | Approved | JON MCHUGH |
| Final | 7/8/2025 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 7/8/2025 | Approved | JON MCHUGH |
| MERV13>=Final | 7/8/2025 | Approved | JON MCHUGH |
| Service/Power Release | 7/8/2025 | Approved | JON MCHUGH |
| Final | 7/22/2025 | OK to Issue CofO | JON MCHUGH |