678 1/2 E 45TH ST 90011
Certificate Information: 678 1/2 E 45TH ST 90011
- Application / Permit
- 24010-20000-02265
- Plan Check / Job No.
- B24VN07451
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story detached ADU per Ordinance (LAMC 12.22 A.33(b)(1))
- Permit Issued
- Issued on 7/29/2025
- Issuing Office
- Current Status
- Issued on 7/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 6/26/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 7/9/2024 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/15/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 12/5/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 1/9/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 7/16/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 7/28/2025 | HOOMAN HAJIZADEH |
| Issued | 7/29/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/17/2024 | RICARDO BOHORQUEZ |
| Community Plan Implem. Overlay | Cleared | 9/18/2024 | IRA RODRIGUEZ |
| Community Plan Implem. Overlay | Cleared | 9/19/2024 | DYNL MIRANDA |
| Address approval | Cleared | 9/20/2024 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 9/20/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/20/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2024 | WALLIE JONG |
| Sewer availability | Cleared | 9/25/2024 | WALLIE JONG |
| Flood clearance | Cleared | 6/4/2025 | ELYSE GREPO |
| Community Plan Implem. Overlay | Cleared | 6/10/2025 | IRA RODRIGUEZ |
| Address approval | Cleared | 6/12/2025 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 6/12/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/17/2025 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 6/18/2025 | ANACANY HURTADO |
| Community Plan Implem. Overlay | Cleared | 6/23/2025 | BRANDON WONG |
| Community Plan Implem. Overlay | Cleared | 7/2/2025 | OSCAR CASTRO |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 1752 TEMPLE CITY, CA 91780 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 8/20/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 8/20/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | LUIS CASTRO |
| Deputy Wood Construction | 9/10/2025 | Conditional Approval | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/21/2025 | Partial Inspection | JOHN QUINTANILLA |
| Insulation | 10/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 10/23/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 10/27/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 10/31/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/18/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/18/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/25/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/25/2026 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 2/26/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/5/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/5/2026 | Approved | ALEJANDRO DE ARTOLA |